Back to Explorer
Permitted
Howard Energy Partners, LLC
9805 Katy Freeway Suite 600, Houston (Harris County)
TDLR Project: 4
Match confidence95%
tdlr_geo
📊Project Metrics
TDLR #TABS2025012032$5.2M
Total Value
Started:Feb 17, 2025
Last activity:Mar 18, 2026
Duration:394 days
Project timeline
2025
Feb 17
1 yr ago
TDLR Project: Origin Bank
TDLR Project • Review Complete
Valuation: $1.7M
Linked via: Merged
Open recordFebruary 17, 2025
TABS2025012032
2025
Feb 20
1 yr ago
TDLR Project: Murphy Oil Corporation Renovation - LVL 1 Locker Rooms
TDLR Project • Inspection Complete
Valuation: $500K
Linked via: Merged
Open recordFebruary 20, 2025
TABS2025012385
2025
Apr 1
12 mos ago
Construction Start
TDLR Project • Projected start
Work itemOrigin Bank
Start Apr 1, 2025→End Jun 2, 2025
April 1, 2025
TABS2025012032
2025
Apr 3
12 mos ago
Construction Start
TDLR Project • Projected start
Work itemMurphy Oil Corporation Renovation - LVL 1 Locker Rooms
Start Apr 3, 2025→End May 28, 2025
April 3, 2025
TABS2025012385
2025
Apr 4
12 mos ago
TDLR Project: Howard Energy Partners, LLC
TDLR Project • Review Complete
Valuation: $550K
Linked via: Merged
Open recordApril 4, 2025
TABS2025015919
2025
May 15
10 mos ago
Construction Start
TDLR Project • Projected start
Work itemHoward Energy Partners, LLC
Start May 15, 2025→End Jul 15, 2025
May 15, 2025
TABS2025015919
2025
May 28
10 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemMurphy Oil Corporation Renovation - LVL 1 Locker Rooms
Start Apr 3, 2025→End May 28, 2025
May 28, 2025
TABS2025012385
2025
Jun 2
10 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemOrigin Bank
Start Apr 1, 2025→End Jun 2, 2025
June 2, 2025
TABS2025012032
2025
Jul 15
8 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemHoward Energy Partners, LLC
Start May 15, 2025→End Jul 15, 2025
July 15, 2025
TABS2025015919
2026
Mar 18
6 days ago
TDLR Project: Murphy Oil Renovation - Level 09
TDLR Project • Project Registered
Valuation: $2.5M
Link confidence: 100%
Open recordMarch 18, 2026
TABS2026015335
2026
Apr 30
1 mo from now
Construction Start
TDLR Project • Projected start
Work itemMurphy Oil Renovation - Level 09
Start Apr 30, 2026→End Aug 21, 2026
April 30, 2026
TABS2026015335
2026
Aug 21
5 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemMurphy Oil Renovation - Level 09
Start Apr 30, 2026→End Aug 21, 2026
August 21, 2026
TABS2026015335
Linked records by source
TDLR Projects (4)
(source: tabs_projects)Origin Bank
Review Complete • Feb 17, 2025
TABS2025012032
Description: Interior Renovation of an existing interior build-out.
Facility: Murphy Building
Estimated cost: $1.7M
Sq Ft: 15,744
Murphy Oil Corporation Renovation - LVL 1 Locker Rooms
Inspection Complete • Feb 20, 2025
TABS2025012385
Description: Interior locker room demolition and new build out of level one on multi-tenant floor in a mid-rise existing office building.
Facility: Murphy Oil
Design firm: House and Robertson Architects
Estimated cost: $500K
Sq Ft: 632
Howard Energy Partners, LLC
Review Complete • Apr 4, 2025
TABS2025015919
Description: Interior renovation of the south-west portion of the sixth floor of an existing 14 story building.
Facility: 9805 Katy Frwy
Design firm: HOK
Estimated cost: $550K
Sq Ft: 5,378
Murphy Oil Renovation - Level 09
Project Registered • Mar 18, 2026
TABS2026015335
Description: Partial interior office space demolition and renovation on Level 09 on a single tenant floor in a mid-rise building.
Facility: Murphy Oil
Design firm: House & Robertson Architects
Estimated cost: $2.5M
Sq Ft: 20,478
Explore Related Projects
Quick Actions
Registered Accessibility Specialist
BRIAN GARY,STANTON (RAS #25)
607 ZOE ST, HOUSTON, TX 77020
Companies & Contacts
🏢
Owner
MetroNational
🏢
Owner
MURPHY DISTRICT NO 1 ET AL
🏢
Design firm
House and Robertson Architects
🏢
Design firm
HOK
Explore Area
Project metadata
- First activity
- February 17, 2025
- Last activity
- March 18, 2026