📊Project Metrics
TDLR #TABS2025002649$20.6M
Total Value
Started:Oct 7, 2024
Last activity:Mar 19, 2026
Duration:528 days
Project timeline
2024
Oct 7
1 yr ago
TDLR Project: Atlantic Aviation
TDLR Project • Project Closed
Valuation: $2.0M
Linked via: Merged
Open recordOctober 7, 2024
TABS2025002649
2024
Oct 18
1 yr ago
Construction Start
TDLR Project • Projected start
Work itemAtlantic Aviation
Start Oct 18, 2024→End Feb 28, 2025
October 18, 2024
TABS2025002649
2025
Jan 21
1 yr ago
January 21, 2025
TABS2025010027
2025
Jan 21
1 yr ago
Construction Start
TDLR Project • Projected start
Work itemMaxor
Start Jan 21, 2025→End Jun 1, 2025
January 21, 2025
TABS2025010027
2025
Jan 30
1 yr ago
TDLR Project: 8th Floor Corridor
TDLR Project • Review Complete
Valuation: $200K
Linked via: Merged
Open recordJanuary 30, 2025
TABS2025010700
2025
Jan 30
1 yr ago
Construction Start
TDLR Project • Projected start
Work item8th Floor Corridor
Start Jan 30, 2025→End Jun 1, 2025
January 30, 2025
TABS2025010700
2025
Feb 28
1 yr ago
Expected Completion
TDLR Project • Projected completion
Work itemAtlantic Aviation
Start Oct 18, 2024→End Feb 28, 2025
February 28, 2025
TABS2025002649
2025
Apr 25
11 mos ago
TDLR Project: Lockton - Granite Park 6
TDLR Project • Review Complete
Valuation: $7.0M
Linked via: Merged
Open recordApril 25, 2025
TABS2025017539
2025
May 2
11 mos ago
TDLR Project: SIMPSON STRONG-TIE
TDLR Project • Inspection Complete
Valuation: $5.0M
Linked via: Merged
Open recordMay 2, 2025
TABS2025018062
2025
Jun 1
10 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemMaxor
Start Jan 21, 2025→End Jun 1, 2025
June 1, 2025
TABS2025010027
2025
Jun 1
10 mos ago
Expected Completion
TDLR Project • Projected completion
Work item8th Floor Corridor
Start Jan 30, 2025→End Jun 1, 2025
June 1, 2025
TABS2025010700
2025
Jun 16
9 mos ago
Construction Start
TDLR Project • Projected start
Work itemSIMPSON STRONG-TIE
Start Jun 16, 2025→End Nov 14, 2025
June 16, 2025
TABS2025018062
2025
Jun 24
9 mos ago
TDLR Project: Midea Dallas HVAC Center
TDLR Project • Review Complete
Valuation: $2.3M
Linked via: Merged
Open recordJune 24, 2025
TABS2025021926
2025
Jun 24
9 mos ago
TDLR Project: 11th Floor Corridor
TDLR Project • Review Complete
Valuation: $154K
Linked via: Merged
Open recordJune 24, 2025
TABS2025021908
2025
Jun 30
9 mos ago
Construction Start
TDLR Project • Projected start
Work itemLockton - Granite Park 6
Start Jun 30, 2025→End Apr 1, 2026
June 30, 2025
TABS2025017539
2025
Jul 7
9 mos ago
Construction Start
TDLR Project • Projected start
Work itemMidea Dallas HVAC Center
Start Jul 7, 2025→End Oct 25, 2025
July 7, 2025
TABS2025021926
2025
Jul 7
9 mos ago
Construction Start
TDLR Project • Projected start
Work item11th Floor Corridor
Start Jul 7, 2025→End Sep 26, 2025
July 7, 2025
TABS2025021908
2025
Aug 27
7 mos ago
TDLR Project: Pax & Beneficia at Granite Park 6
TDLR Project • Review Complete
Valuation: $450K
Linked via: Merged
Open recordAugust 27, 2025
TABS2025026886
2025
Sep 26
6 mos ago
Expected Completion
TDLR Project • Projected completion
Work item11th Floor Corridor
Start Jul 7, 2025→End Sep 26, 2025
September 26, 2025
TABS2025021908
2025
Oct 7
6 mos ago
Construction Start
TDLR Project • Projected start
Work itemPax & Beneficia at Granite Park 6
Start Oct 7, 2025→End Jan 29, 2026
October 7, 2025
TABS2025026886
2025
Oct 25
5 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemMidea Dallas HVAC Center
Start Jul 7, 2025→End Oct 25, 2025
October 25, 2025
TABS2025021926
2025
Nov 14
4 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemSIMPSON STRONG-TIE
Start Jun 16, 2025→End Nov 14, 2025
November 14, 2025
TABS2025018062
2026
Jan 29
2 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemPax & Beneficia at Granite Park 6
Start Oct 7, 2025→End Jan 29, 2026
January 29, 2026
TABS2025026886
2026
Mar 13
11 days ago
TDLR Project: Aven Hospitality
TDLR Project • Project Registered
Valuation: $2.6M
Link confidence: 100%
Open recordMarch 13, 2026
TABS2026014900
2026
Mar 18
6 days ago
Construction Start
TDLR Project • Projected start
Work itemRithum
Start Mar 18, 2026→End May 21, 2026
March 18, 2026
TABS2026015428
2026
Mar 19
5 days ago
TDLR Project: Rithum
TDLR Project • Project Registered
Valuation: $108K
Link confidence: 100%
Open recordMarch 19, 2026
TABS2026015428
2026
Apr 1
8 days from now
Expected Completion
TDLR Project • Projected completion
Work itemLockton - Granite Park 6
Start Jun 30, 2025→End Apr 1, 2026
April 1, 2026
TABS2025017539
2026
Apr 1
8 days from now
Construction Start
TDLR Project • Projected start
Work itemAven Hospitality
Start Apr 1, 2026→End Sep 16, 2026
April 1, 2026
TABS2026014900
2026
May 21
2 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemRithum
Start Mar 18, 2026→End May 21, 2026
May 21, 2026
TABS2026015428
2026
Sep 16
6 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemAven Hospitality
Start Apr 1, 2026→End Sep 16, 2026
September 16, 2026
TABS2026014900
Linked records by source
TDLR Projects (10)
(source: tabs_projects)Atlantic Aviation
Project Closed • Oct 7, 2024
TABS2025002649
Description: Tenant Improvement
Facility: Granite Park 6
Design firm: ENTOS
Estimated cost: $2.0M
Sq Ft: 21,683
Maxor
Project Closed • Jan 21, 2025
TABS2025010027
Description: Tenant Improvement
Facility: Granite Park 6
Design firm: ENTOS
Estimated cost: $810K
Sq Ft: 6,110
8th Floor Corridor
Review Complete • Jan 30, 2025
TABS2025010700
Description: Capital Improvement
Facility: Granite Park 6
Design firm: Entos Design
Estimated cost: $200K
Sq Ft: 1,376
Lockton - Granite Park 6
Review Complete • Apr 25, 2025
TABS2025017539
Description: First time office tenant finish out
Facility: Granite Park 6
Estimated cost: $7.0M
Sq Ft: 61,149
SIMPSON STRONG-TIE
Inspection Complete • May 2, 2025
TABS2025018062
Description: RENOVAION OF EXISTING INTERIOR OFFICE SPACE
Facility: GRANITE PARK 6
Estimated cost: $5.0M
Sq Ft: 30,500
Midea Dallas HVAC Center
Review Complete • Jun 24, 2025
TABS2025021926
Description: First finish-out of existing space in existing building. Project includes office space, training space, and a sales/exhibition space for showing equipment.
Facility: Granite Park 6
Design firm: Entos Design
Estimated cost: $2.3M
Sq Ft: 23,610
11th Floor Corridor
Review Complete • Jun 24, 2025
TABS2025021908
Description: Capital Improvement
Facility: Granite Park 6
Design firm: Entos Design
Estimated cost: $154K
Sq Ft: 1,408
Pax & Beneficia at Granite Park 6
Review Complete • Aug 27, 2025
TABS2025026886
Description: Interior finish out of coffee shop. Scope includes new restrooms, prep kitchen and bar area.
Facility: Granite Park 6
Design firm: Sookoor Design Studio
Estimated cost: $450K
Sq Ft: 1,800
Aven Hospitality
Project Registered • Mar 13, 2026
TABS2026014900
Description: Suite 1400 = 22,088 Suite 1550 = 11,268
Facility: Granite Park 6
Design firm: Entos Design
Estimated cost: $2.6M
Sq Ft: 33,356
Rithum
Project Registered • Mar 19, 2026
TABS2026015428
Description: Renovation of approximately 4,521 SF of existing office space.
Facility: Granite Park 6
Design firm: BHA Studio
Estimated cost: $108K
Sq Ft: 4,521
Explore Related Projects
Quick Actions
Registered Accessibility Specialist
MICHAEL LYNN,KELLEY (RAS #1472)
780 N WATTERS RD STE 150, ALLEN, TX 75013
Companies & Contacts
🏢
Owner
Granite Park NM/GP VI LP
🏢
Owner
Granite Properties
🏢
Design firm
ENTOS
🏢
Design firm
Entos Design
🏢
Owner
Lockton
🏢
Owner
Granite Park VI LP
🏢
Design firm
Sookoor Design Studio
🏢
Design firm
BHA Studio
Explore Area
Project metadata
- First activity
- October 7, 2024
- Last activity
- March 19, 2026