๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
NORMAL POWER REPLACEMENT PDC-K
6720 BERTNER AVE., Houston, TX 77030, Houston, TX, 77030
Completed100%
๐Project Metrics
TDLR #EABPRJB1804443$1.7M
Project Value
โ
Square Feet
โ
Cost/SqFt
11 months
Duration
Registered:Dec 7, 2010
Start:Jan 1, 2011
Target:Dec 1, 2011
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Replace switchgear and power distribution centers for normal power in Sector K. First of 5 phases.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 7, 2010
Construction Start
January 1, 2011
Expected Completion
December 1, 2011
๐Related Projects
๐๏ธSame Design Firm
$6.3M totalProperty Owner
๐ค
ST. LUKE'S EPISCOPAL HOSPITAL
View company profile
CHUCK AYOUB 6720 BERTNER AVE., HOUSTON, TX 77030
Design Firm
๐๏ธ
CURRY BOUDREAUX ARCHITECTS LLP
4 projects ยท $6.3M
View all projects
RICHERD PALUMBO, AIA 5009 CAROLINE, SUITE 200, HOUSTON, TX 77004