📋Project Registered🏗️ New Construction💵 This project is privately funded, on private land for private use.

Manvel Fuel Express

19310 Hwy 6, Manvel, TX 77578, Manvel, TX, 77578
Pre-Construction15%

📊Project Metrics

TDLR #TABS2019004438
$850K
Project Value
4,510
Square Feet
$188/sqft
Cost/SqFt
6 months
Duration
Registered:Feb 8, 2019
Start:Mar 31, 2019
Target:Sep 30, 2019
📋

Project Registered

Project has been registered with TDLR and is in pre-construction phase

📋Scope of Work

Ground up construction of a C-store

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
February 8, 2019
Construction Start
March 31, 2019
Expected Completion
September 30, 2019