Erickson Dental
210 O'Connor Ridge Blvd, Irving, TX 75062, Irving, TX, 75062
Completed100%
๐Project Metrics
TDLR #TABS2020015988$415K
Project Value
3,526
Square Feet
$118/sqft
Cost/SqFt
6 months
Duration
Registered:Apr 21, 2020
Start:May 1, 2020
Target:Nov 1, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Interior finish out of dental office
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
April 21, 2020
Construction Start
May 1, 2020
Expected Completion
November 1, 2020