Medical District PK-8 Stem School - Phase 1.5

6516 Forest Park Road, Dallas, TX 75235, Dallas, TX, 75235
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023002961
$1.3M
Project Value
6,000
Square Feet
$210/sqft
Cost/SqFt
1y 6mo
Duration
Registered:Oct 11, 2022
Start:Aug 16, 2022
Target:Feb 21, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Renovation of existing second floor shell space of a building in the medical district. Shell space to be turned into (2) classrooms, a steam lab, restrooms, offices, and (1) meeting room

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 11, 2022
Construction Start
August 16, 2022
Expected Completion
February 21, 2024