Dr. Walter - Phase 3 CP-FY22-014

7703 Floyd Curl Drive, San Antonio, TX 78229, San Antonio, TX, 78229
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023015055
$105K
Project Value
359
Square Feet
$292/sqft
Cost/SqFt
3 months
Duration
Registered:Mar 27, 2023
Start:Apr 28, 2023
Target:Aug 1, 2023
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

Office remodel

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 27, 2023
Construction Start
April 28, 2023
Expected Completion
August 1, 2023