โœ…Inspection Complete๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Off Boston Development

350 Pine Street Suite 720, Beaumont, TX 77701, Beaumont, TX, 77701
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2023023306
$2.8M
Project Value
8,120
Square Feet
$351/sqft
Cost/SqFt
1 year
Duration
Registered:Jul 11, 2023
Start:Aug 28, 2023
Target:Aug 28, 2024
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

retail cottages for sale

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 11, 2023
Construction Start
August 28, 2023
Expected Completion
August 28, 2024