โ
Inspection Complete๐ง Additions to Existing Building๐ต This project is privately funded, on private land for private use.
Saginaw Kids Dentistry
600 E. Bailey Boswell Rd. suite 100, Fort Worth, TX, 76131
Final Inspection85%
๐Project Metrics
TDLR #TABS2025013713$261K
Project Value
2,581
Square Feet
$101/sqft
Cost/SqFt
3 months
Duration
Registered:Mar 10, 2025
Start:Apr 10, 2025
Target:Jul 14, 2025
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Interior finish out of existing dental office
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
March 10, 2025
Review Complete
+284dMarch 10, 2025
Inspection Complete
December 19, 2025
Construction Start
April 10, 2025
Expected Completion
July 14, 2025
๐Related Projects
๐Nearby Projects
Within 1 kmProperty Owner
๐ค
ELIAS CHAHINE
Contact: Elias Chahine
View company profile