Back to Explorer
Permitted
Domino's - Leander, TX
18145 Ronald W Reagan Blvd Suite 110, Leander (Williamson County)
TDLR Project: 8
Match confidence95%
tdlr_geo
📊Project Metrics
TDLR #TABS2021019980$6.5M
Total Value
Started:Jul 16, 2021
Last activity:Mar 19, 2026
Duration:1707 days
Project timeline
2021
Jul 16
5 yrs ago
TDLR Project: Shops at Ronald
TDLR Project • Review Complete
Valuation: $1.7M
Linked via: Merged
Open recordJuly 16, 2021
TABS2021019980
2021
Aug 1
5 yrs ago
Construction Start
TDLR Project • Projected start
Work itemShops at Ronald
Start Aug 1, 2021→End Mar 1, 2022
August 1, 2021
TABS2021019980
2022
Mar 1
4 yrs ago
Expected Completion
TDLR Project • Projected completion
Work itemShops at Ronald
Start Aug 1, 2021→End Mar 1, 2022
March 1, 2022
TABS2021019980
2024
Mar 1
2 yrs ago
Construction Start
TDLR Project • Projected start
Work itemValley Vista Center Phase 2
Start Mar 1, 2024→End Mar 13, 2026
March 1, 2024
TABS2026015402
2025
May 2
11 mos ago
TDLR Project: Smiling Donuts
TDLR Project • Project Closed
Valuation: $130K
Linked via: Merged
Open recordMay 2, 2025
TABS2025018048
2025
Jun 2
10 mos ago
TDLR Project: Baskin Robbins - Leander
TDLR Project • Review Complete
Valuation: $200K
Linked via: Merged
Open recordJune 2, 2025
TABS2025020319
2025
Jun 13
9 mos ago
TDLR Project: Desi Bites Leander
TDLR Project • Review Complete
Valuation: $500K
Linked via: Merged
Open recordJune 13, 2025
TABS2025021301
2025
Jul 1
9 mos ago
Construction Start
TDLR Project • Projected start
Work itemSmiling Donuts
Start Jul 1, 2025→End Sep 1, 2025
July 1, 2025
TABS2025018048
2025
Jul 15
8 mos ago
Construction Start
TDLR Project • Projected start
Work itemDesi Bites Leander
Start Jul 15, 2025→End Jan 31, 2026
July 15, 2025
TABS2025021301
2025
Jul 31
8 mos ago
TDLR Project: Skips leander
TDLR Project • Project Registered
Valuation: $120K
Linked via: Merged
Open recordJuly 31, 2025
TABS2025024873
2025
Aug 28
7 mos ago
TDLR Project: Tenant Build-Out for Kumon
TDLR Project • Review Complete
Valuation: $100K
Linked via: Merged
Open recordAugust 28, 2025
TABS2025026998
2025
Aug 31
7 mos ago
Construction Start
TDLR Project • Projected start
Work itemBaskin Robbins - Leander
Start Aug 31, 2025→End Dec 31, 2025
August 31, 2025
TABS2025020319
2025
Sep 1
7 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemSmiling Donuts
Start Jul 1, 2025→End Sep 1, 2025
September 1, 2025
TABS2025018048
2025
Oct 7
6 mos ago
TDLR Project: Domino's - Leander, TX
TDLR Project • Review Complete
Valuation: $400K
Linked via: Merged
Open recordOctober 7, 2025
TABS2026002783
2025
Oct 27
5 mos ago
Construction Start
TDLR Project • Projected start
Work itemDomino's - Leander, TX
Start Oct 27, 2025→End Dec 19, 2025
October 27, 2025
TABS2026002783
2025
Nov 1
5 mos ago
Construction Start
TDLR Project • Projected start
Work itemTenant Build-Out for Kumon
Start Nov 1, 2025→End Dec 1, 2025
November 1, 2025
TABS2025026998
2025
Dec 1
4 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemTenant Build-Out for Kumon
Start Nov 1, 2025→End Dec 1, 2025
December 1, 2025
TABS2025026998
2025
Dec 19
3 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemDomino's - Leander, TX
Start Oct 27, 2025→End Dec 19, 2025
December 19, 2025
TABS2026002783
2025
Dec 31
3 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemBaskin Robbins - Leander
Start Aug 31, 2025→End Dec 31, 2025
December 31, 2025
TABS2025020319
2025
Dec 31
3 mos ago
Construction Start
TDLR Project • Projected start
Work itemSkips leander
Start Dec 31, 2025→End Dec 31, 2026
December 31, 2025
TABS2025024873
2026
Jan 31
2 mos ago
Expected Completion
TDLR Project • Projected completion
Work itemDesi Bites Leander
Start Jul 15, 2025→End Jan 31, 2026
January 31, 2026
TABS2025021301
2026
Mar 13
11 days ago
Expected Completion
TDLR Project • Projected completion
Work itemValley Vista Center Phase 2
Start Mar 1, 2024→End Mar 13, 2026
March 13, 2026
TABS2026015402
2026
Mar 19
5 days ago
TDLR Project: Valley Vista Center Phase 2
TDLR Project • Project Registered
Valuation: $3.4M
Link confidence: 100%
Open recordMarch 19, 2026
TABS2026015402
2026
Dec 31
9 mos from now
Expected Completion
TDLR Project • Projected completion
Work itemSkips leander
Start Dec 31, 2025→End Dec 31, 2026
December 31, 2026
TABS2025024873
Linked records by source
TDLR Projects (8)
(source: tabs_projects)Shops at Ronald
Review Complete • Jul 16, 2021
TABS2021019980
Description: Ground up shell retail pre engineered metal building with associated parking and landscaping.
Facility: Shops at Ronald Reagan
Design firm: Modus Architecture, LLC
Estimated cost: $1.7M
Sq Ft: 18,340
Smiling Donuts
Project Closed • May 2, 2025
TABS2025018048
Description: First tenant generation finish out for a donut shop
Facility: Shops at Ronald Reagan
Design firm: RB Architect PLLC
Estimated cost: $130K
Sq Ft: 1,000
Baskin Robbins - Leander
Review Complete • Jun 2, 2025
TABS2025020319
Description: Interior build-out in a tenant space for a new Baskin-Robbins
Facility: Shops at Ronald Reagan
Design firm: Reese Design Services
Estimated cost: $200K
Sq Ft: 1,566
Desi Bites Leander
Review Complete • Jun 13, 2025
TABS2025021301
Description: First Generation Restaurant Finish Out with Dining, Sales, Commercial Kitchen and ADA/TAS Restroom
Facility: Desi Bites Leander
Design firm: Studio RM Architecture & Planning, PLLC
Estimated cost: $500K
Sq Ft: 2,550
Skips leander
Project Registered • Jul 31, 2025
TABS2025024873
Description: Interior finish
Facility: Skips leander
Estimated cost: $120K
Sq Ft: 2,700
Tenant Build-Out for Kumon
Review Complete • Aug 28, 2025
TABS2025026998
Description: Tenant Improvement Plan in an existing strip center for a "Kumon" Learning Center.
Facility: Shops at Reagan
Estimated cost: $100K
Sq Ft: 1,600
Domino's - Leander, TX
Review Complete • Oct 7, 2025
TABS2026002783
Description: Interior remodel of an existing space in a new strip center for a buildout of Domino's Pizza
Facility: Shops on Reagan
Design firm: Oculus Inc
Estimated cost: $400K
Sq Ft: 1,844
Valley Vista Center Phase 2
Project Registered • Mar 19, 2026
TABS2026015402
Description: Site improvements to include utility installation, pavement, sidewalks and a 18,340 sf building.
Facility: Shops on Ronald Reagan
Design firm: Jamison Civil Engineering LLC
Estimated cost: $3.4M
Sq Ft: 18,340
Quick Actions
Companies & Contacts
🏢
Owner
Shops on Ronald Reagan LLC
🏢
Owner
Shops at Ronald Reagan
🏢
Design firm
Modus Architecture, LLC
🏢
Owner
Huntington
🏢
Design firm
RB Architect PLLC
🏢
Design firm
Reese Design Services
🏢
Owner
R3D Desi Flavors LLC dba Desi Bites Leander
🏢
Design firm
Studio RM Architecture & Planning, PLLC
🏢
Owner
Andy bawani
🏢
Design firm
Oculus Inc
🏢
Design firm
Jamison Civil Engineering LLC
Explore Area
Project metadata
- First activity
- July 16, 2021
- Last activity
- March 19, 2026