Back to Explorer
Permitted

The Original Lovett College Renovation

6100 Main St. Houston, TX 77005, Houston, TX 77005, Houston (Harris County)

TDLR Project: 46
Match confidence95%
tdlr_geo

📍Location & Views

Open in MapsGet Directions|29.72063, -95.39375

📊Project Metrics

TDLR #EABPRJA9808796
$242.3M
Total Value
Started:Feb 26, 2009
Last activity:Mar 19, 2026
Duration:6230 days

Project timeline

2009
Feb 26
17 yrs ago
TDLR Project: BROCKMAN HALL FOR PHYSICS
TDLR ProjectProject Closed
Valuation: $49.0M
Linked via: Merged
Open record
February 26, 2009
EABPRJA9808796
2009
Mar 10
17 yrs ago
TDLR Project: DR. PUTNAM LAB RENOVATIONS
TDLR ProjectProject Closed
Valuation: $400K
Linked via: Merged
Open record
March 10, 2009
EABPRJA9809309
2009
Apr 1
17 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemDR. PUTNAM LAB RENOVATIONS
Start Apr 1, 2009End Aug 1, 2009
Open record
April 1, 2009
EABPRJA9809309
2009
May 1
17 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemBROCKMAN HALL FOR PHYSICS
Start May 1, 2009End Feb 1, 2011
Open record
May 1, 2009
EABPRJA9808796
2009
Aug 1
17 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemDR. PUTNAM LAB RENOVATIONS
Start Apr 1, 2009End Aug 1, 2009
Open record
August 1, 2009
EABPRJA9809309
2010
Dec 8
15 yrs ago
TDLR Project: RICE UNIVERSITY HANSZEN MASTER HOUSE
TDLR ProjectProject Closed
Valuation: $100K
Linked via: Merged
Open record
December 8, 2010
EABPRJB1804477
2011
Jan 1
15 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRICE UNIVERSITY HANSZEN MASTER HOUSE
Start Jan 1, 2011End Apr 1, 2011
Open record
January 1, 2011
EABPRJB1804477
2011
Feb 1
15 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemBROCKMAN HALL FOR PHYSICS
Start May 1, 2009End Feb 1, 2011
Open record
February 1, 2011
EABPRJA9808796
2011
Apr 1
15 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRICE UNIVERSITY HANSZEN MASTER HOUSE
Start Jan 1, 2011End Apr 1, 2011
Open record
April 1, 2011
EABPRJB1804477
2017
Apr 1
9 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemSPACE SCIENCE & TECH BLDG RENOVATION
Start Apr 1, 2017End Feb 28, 2019
Open record
April 1, 2017
EABPRJB7815617
2017
Apr 24
9 yrs ago
TDLR Project: SPACE SCIENCE & TECH BLDG RENOVATION
TDLR ProjectInspection Complete
Valuation: $25.3M
Linked via: Merged
Open record
April 24, 2017
EABPRJB7815617
2019
Feb 28
7 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemSPACE SCIENCE & TECH BLDG RENOVATION
Start Apr 1, 2017End Feb 28, 2019
Open record
February 28, 2019
EABPRJB7815617
2019
Mar 7
7 yrs ago
TDLR Project: Martel College Suite 1160
TDLR ProjectProject Closed
Valuation: $250K
Linked via: Merged
Open record
March 7, 2019
TABS2019006459
2019
Mar 7
7 yrs ago
TDLR Project: Duncan College Student Activity Space
TDLR ProjectProject Closed
Valuation: $150K
Linked via: Merged
Open record
March 7, 2019
TABS2019006455
2019
Apr 8
7 yrs ago
TDLR Project: Cohen House Restroom Renovation
TDLR ProjectProject Closed
Valuation: $332K
Linked via: Merged
Open record
April 8, 2019
TABS2019008805
2019
Jun 3
7 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemDuncan College Student Activity Space
Start Jun 3, 2019End Jan 1, 2021
Open record
June 3, 2019
TABS2019006455
2019
Jun 4
7 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemMartel College Suite 1160
Start Jun 4, 2019End Sep 4, 2019
Open record
June 4, 2019
TABS2019006459
2019
Jul 1
7 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemCohen House Restroom Renovation
Start Jul 1, 2019End Aug 10, 2019
Open record
July 1, 2019
TABS2019008805
2019
Aug 10
7 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemCohen House Restroom Renovation
Start Jul 1, 2019End Aug 10, 2019
Open record
August 10, 2019
TABS2019008805
2019
Sep 4
7 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemMartel College Suite 1160
Start Jun 4, 2019End Sep 4, 2019
Open record
September 4, 2019
TABS2019006459
2020
Feb 27
6 yrs ago
TDLR Project: Rice Volleyball Team Room Renovation
TDLR ProjectProject Closed
Valuation: $95K
Linked via: Merged
Open record
February 27, 2020
TABS2020012551
2020
Mar 13
6 yrs ago
TDLR Project: MD ANDERSON BIOLOGY 280: EVANS LAB
TDLR ProjectProject Closed
Valuation: $250K
Linked via: Merged
Open record
March 13, 2020
TABS2020013701
2020
Mar 13
6 yrs ago
TDLR Project: National Research Security Accelerator
TDLR ProjectProject Closed
Valuation: $1.2M
Linked via: Merged
Open record
March 13, 2020
TABS2020013700
2020
Mar 20
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice Volleyball Team Room Renovation
Start Mar 20, 2020End Dec 15, 2020
Open record
March 20, 2020
TABS2020012551
2020
May 1
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemMD ANDERSON BIOLOGY 280: EVANS LAB
Start May 1, 2020End Sep 30, 2020
Open record
May 1, 2020
TABS2020013701
2020
May 1
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemNational Research Security Accelerator
Start May 1, 2020End Sep 30, 2020
Open record
May 1, 2020
TABS2020013700
2020
May 28
6 yrs ago
TDLR Project: APBH Renovations
TDLR ProjectProject Closed
Valuation: $250K
Linked via: Merged
Open record
May 28, 2020
TABS2020018014
2020
Jun 30
6 yrs ago
TDLR Project: Rice University PCF 4
TDLR ProjectProject Closed
Valuation: $500K
Linked via: Merged
Open record
June 30, 2020
TABS2020019842
2020
Jun 30
6 yrs ago
TDLR Project: Rice University PCF 3
TDLR ProjectProject Closed
Valuation: $500K
Linked via: Merged
Open record
June 30, 2020
TABS2020019841
2020
Jun 30
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemAPBH Renovations
Start Jun 30, 2020End Mar 1, 2021
Open record
June 30, 2020
TABS2020018014
2020
Jul 30
6 yrs ago
TDLR Project: Rice University - AT - Keith-Weiss
TDLR ProjectProject Closed
Valuation: $94K
Linked via: Merged
Open record
July 30, 2020
TABS2020021447
2020
Jul 30
6 yrs ago
TDLR Project: Rice Universtity - AT - West Quad
TDLR ProjectProject Closed
Valuation: $94K
Linked via: Merged
Open record
July 30, 2020
TABS2020021439
2020
Aug 1
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice University PCF 4
Start Aug 1, 2020End Sep 30, 2020
Open record
August 1, 2020
TABS2020019842
2020
Aug 1
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice University PCF 3
Start Aug 1, 2020End Sep 30, 2020
Open record
August 1, 2020
TABS2020019841
2020
Aug 17
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice University - AT - Keith-Weiss
Start Aug 17, 2020End Aug 31, 2020
Open record
August 17, 2020
TABS2020021447
2020
Aug 17
6 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice Universtity - AT - West Quad
Start Aug 17, 2020End Aug 31, 2020
Open record
August 17, 2020
TABS2020021439
2020
Aug 31
6 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice University - AT - Keith-Weiss
Start Aug 17, 2020End Aug 31, 2020
Open record
August 31, 2020
TABS2020021447
2020
Aug 31
6 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice Universtity - AT - West Quad
Start Aug 17, 2020End Aug 31, 2020
Open record
August 31, 2020
TABS2020021439
2020
Sep 30
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemMD ANDERSON BIOLOGY 280: EVANS LAB
Start May 1, 2020End Sep 30, 2020
Open record
September 30, 2020
TABS2020013701
2020
Sep 30
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemNational Research Security Accelerator
Start May 1, 2020End Sep 30, 2020
Open record
September 30, 2020
TABS2020013700
2020
Sep 30
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice University PCF 4
Start Aug 1, 2020End Sep 30, 2020
Open record
September 30, 2020
TABS2020019842
2020
Sep 30
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice University PCF 3
Start Aug 1, 2020End Sep 30, 2020
Open record
September 30, 2020
TABS2020019841
2020
Oct 1
5 yrs ago
TDLR Project: Rice Sewall Hall
TDLR ProjectProject Closed
Valuation: $381K
Linked via: Merged
Open record
October 1, 2020
TABS2021001820
2020
Oct 19
5 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice Sewall Hall
Start Oct 19, 2020End Feb 15, 2021
Open record
October 19, 2020
TABS2021001820
2020
Dec 15
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice Volleyball Team Room Renovation
Start Mar 20, 2020End Dec 15, 2020
Open record
December 15, 2020
TABS2020012551
2021
Jan 1
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemDuncan College Student Activity Space
Start Jun 3, 2019End Jan 1, 2021
Open record
January 1, 2021
TABS2019006455
2021
Feb 15
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice Sewall Hall
Start Oct 19, 2020End Feb 15, 2021
Open record
February 15, 2021
TABS2021001820
2021
Mar 1
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemAPBH Renovations
Start Jun 30, 2020End Mar 1, 2021
Open record
March 1, 2021
TABS2020018014
2023
Sep 26
2 yrs ago
TDLR Project: OConner Engineering Huang Kono Basement Renovation
TDLR ProjectProject Closed
Valuation: $150K
Linked via: Merged
Open record
September 26, 2023
TABS2024001735
2023
Oct 30
2 yrs ago
TDLR Project: Rice University McNair Hall Expansion
TDLR ProjectReview Complete
Valuation: $56.7M
Linked via: Merged
Open record
October 30, 2023
TABS2024004284
2023
Oct 30
2 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemOConner Engineering Huang Kono Basement Renovation
Start Oct 30, 2023End Nov 30, 2023
Open record
October 30, 2023
TABS2024001735
2023
Oct 31
2 yrs ago
TDLR Project: Graduate Art Studios
TDLR ProjectProject Closed
Valuation: $247K
Linked via: Merged
Open record
October 31, 2023
TABS2024004377
2023
Nov 6
2 yrs ago
TDLR Project: Rice GRB E225 Kampouri Lab
TDLR ProjectProject Closed
Valuation: $320K
Linked via: Merged
Open record
November 6, 2023
TABS2024004795
2023
Nov 30
2 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemOConner Engineering Huang Kono Basement Renovation
Start Oct 30, 2023End Nov 30, 2023
Open record
November 30, 2023
TABS2024001735
2023
Dec 1
2 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemGraduate Art Studios
Start Dec 1, 2023End Feb 28, 2024
Open record
December 1, 2023
TABS2024004377
2024
Jan 24
2 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice GRB E225 Kampouri Lab
Start Jan 24, 2024End Aug 1, 2024
Open record
January 24, 2024
TABS2024004795
2024
Feb 2
2 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemRice University McNair Hall Expansion
Start Feb 2, 2024End Jan 2, 2026
Open record
February 2, 2024
TABS2024004284
2024
Feb 28
2 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemGraduate Art Studios
Start Dec 1, 2023End Feb 28, 2024
Open record
February 28, 2024
TABS2024004377
2024
Aug 1
2 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice GRB E225 Kampouri Lab
Start Jan 24, 2024End Aug 1, 2024
Open record
August 1, 2024
TABS2024004795
2024
Sep 25
1 yr ago
TDLR Project: Anderson Hall Accessible Ramp
TDLR ProjectReview Complete
Valuation: $257K
Linked via: Merged
Open record
September 25, 2024
TABS2025001841
2024
Dec 10
1 yr ago
TDLR Project: Gibbs Recreation and Wellness Center
TDLR ProjectReview Complete
Valuation: $90K
Linked via: Merged
Open record
December 10, 2024
TABS2025007312
2024
Dec 11
1 yr ago
TDLR Project: Cannady Hall Shop Office
TDLR ProjectProject Closed
Valuation: $60K
Linked via: Merged
Open record
December 11, 2024
TABS2025007448
2024
Dec 16
1 yr ago
Construction Start
TDLR ProjectProjected start
Work itemAnderson Hall Accessible Ramp
Start Dec 16, 2024End Mar 18, 2025
Open record
December 16, 2024
TABS2025001841
2025
Jan 14
1 yr ago
TDLR Project: Rice Boulevard HAWK Crossing
TDLR ProjectInspection Complete
Valuation: $250K
Linked via: Merged
Open record
January 14, 2025
TABS2025009493
2025
Feb 1
1 yr ago
Construction Start
TDLR ProjectProjected start
Work itemGibbs Recreation and Wellness Center
Start Feb 1, 2025End May 1, 2025
Open record
February 1, 2025
TABS2025007312
2025
Feb 13
1 yr ago
TDLR Project: Rice DBH 276 Lab
TDLR ProjectReview Complete
Valuation: $300K
Linked via: Merged
Open record
February 13, 2025
TABS2025011844
2025
Feb 14
1 yr ago
Construction Start
TDLR ProjectProjected start
Work itemCannady Hall Shop Office
Start Feb 14, 2025End Jul 4, 2025
Open record
February 14, 2025
TABS2025007448
2025
Feb 17
1 yr ago
TDLR Project: Rice Moody Center For Student Life & Opportunity Phase I
TDLR ProjectReview Complete
Valuation: $285K
Linked via: Merged
Open record
February 17, 2025
TABS2025012057
2025
Feb 24
1 yr ago
TDLR Project: Women's Golf Locker Room
TDLR ProjectProject Closed
Valuation: $101K
Linked via: Merged
Open record
February 24, 2025
TABS2025012590
2025
Feb 24
1 yr ago
Construction Start
TDLR ProjectProjected start
Work itemRice DBH 276 Lab
Start Feb 24, 2025End Jul 25, 2025
Open record
February 24, 2025
TABS2025011844
2025
Mar 1
1 yr ago
Construction Start
TDLR ProjectProjected start
Work itemRice Boulevard HAWK Crossing
Start Mar 1, 2025End Aug 31, 2025
Open record
March 1, 2025
TABS2025009493
2025
Mar 3
1 yr ago
TDLR Project: GRB 3rd Floor Autoclave
TDLR ProjectReview Complete
Valuation: $98K
Linked via: Merged
Open record
March 3, 2025
TABS2025013201
2025
Mar 7
1 yr ago
TDLR Project: Brockman B13 Jo Lab
TDLR ProjectProject Closed
Valuation: $220K
Linked via: Merged
Open record
March 7, 2025
TABS2025013599
2025
Mar 10
1 yr ago
TDLR Project: RICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
TDLR ProjectReview Complete
Valuation: $4.1M
Linked via: Merged
Open record
March 10, 2025
TABS2025013729
2025
Mar 10
1 yr ago
TDLR Project: RICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
TDLR ProjectReview Complete
Valuation: $192K
Linked via: Merged
Open record
March 10, 2025
TABS2025013727
2025
Mar 18
1 yr ago
Expected Completion
TDLR ProjectProjected completion
Work itemAnderson Hall Accessible Ramp
Start Dec 16, 2024End Mar 18, 2025
Open record
March 18, 2025
TABS2025001841
2025
Mar 20
1 yr ago
TDLR Project: Rice Keck 213 Glasscock Lab
TDLR ProjectProject Closed
Valuation: $650K
Linked via: Merged
Open record
March 20, 2025
TABS2025014750
2025
Mar 31
12 mos ago
TDLR Project: Lovett College Renovations
TDLR ProjectProject Closed
Valuation: $930K
Linked via: Merged
Open record
March 31, 2025
TABS2025015503
2025
Apr 15
11 mos ago
TDLR Project: Pirie & SEA Lab Build-Out
TDLR ProjectReview Complete
Valuation: $1.6M
Linked via: Merged
Open record
April 15, 2025
TABS2025016697
2025
May 1
11 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemGibbs Recreation and Wellness Center
Start Feb 1, 2025End May 1, 2025
Open record
May 1, 2025
TABS2025007312
2025
May 1
11 mos ago
Construction Start
TDLR ProjectProjected start
Work itemGRB 3rd Floor Autoclave
Start May 1, 2025End Dec 31, 2025
Open record
May 1, 2025
TABS2025013201
2025
May 1
11 mos ago
Construction Start
TDLR ProjectProjected start
Work itemBrockman B13 Jo Lab
Start May 1, 2025End Aug 31, 2025
Open record
May 1, 2025
TABS2025013599
2025
May 6
11 mos ago
TDLR Project: Rice Ghonasgi Lab Renovation s MEB
TDLR ProjectReview Complete
Valuation: $170K
Linked via: Merged
Open record
May 6, 2025
TABS2025018272
2025
May 8
11 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice Moody Center For Student Life & Opportunity Phase I
Start May 8, 2025End Jun 7, 2027
Open record
May 8, 2025
TABS2025012057
2025
May 15
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemWomen's Golf Locker Room
Start May 15, 2025End Aug 25, 2025
Open record
May 15, 2025
TABS2025012590
2025
May 19
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemLovett College Renovations
Start May 19, 2025End Aug 4, 2025
Open record
May 19, 2025
TABS2025015503
2025
May 28
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemPirie & SEA Lab Build-Out
Start May 28, 2025End Dec 5, 2025
Open record
May 28, 2025
TABS2025016697
2025
Jun 1
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
Start Jun 1, 2025End Jun 1, 2026
Open record
June 1, 2025
TABS2025013729
2025
Jun 1
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
Start Jun 1, 2025End Jun 1, 2026
Open record
June 1, 2025
TABS2025013727
2025
Jun 1
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice Ghonasgi Lab Renovation s MEB
Start Jun 1, 2025End Aug 30, 2025
Open record
June 1, 2025
TABS2025018272
2025
Jun 9
10 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice Keck 213 Glasscock Lab
Start Jun 9, 2025End Sep 30, 2025
Open record
June 9, 2025
TABS2025014750
2025
Jul 4
9 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemCannady Hall Shop Office
Start Feb 14, 2025End Jul 4, 2025
Open record
July 4, 2025
TABS2025007448
2025
Jul 8
9 mos ago
TDLR Project: Anderson Hall Millwork
TDLR ProjectReview Complete
Valuation: $284K
Linked via: Merged
Open record
July 8, 2025
TABS2025023008
2025
Jul 25
8 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice DBH 276 Lab
Start Feb 24, 2025End Jul 25, 2025
Open record
July 25, 2025
TABS2025011844
2025
Aug 4
8 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemLovett College Renovations
Start May 19, 2025End Aug 4, 2025
Open record
August 4, 2025
TABS2025015503
2025
Aug 8
8 mos ago
TDLR Project: Rice University TDSP Renovation
TDLR ProjectProject Registered
Valuation: $600K
Linked via: Merged
Open record
August 8, 2025
TABS2025025448
2025
Aug 25
7 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemWomen's Golf Locker Room
Start May 15, 2025End Aug 25, 2025
Open record
August 25, 2025
TABS2025012590
2025
Aug 30
7 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice Ghonasgi Lab Renovation s MEB
Start Jun 1, 2025End Aug 30, 2025
Open record
August 30, 2025
TABS2025018272
2025
Aug 31
7 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice Boulevard HAWK Crossing
Start Mar 1, 2025End Aug 31, 2025
Open record
August 31, 2025
TABS2025009493
2025
Aug 31
7 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemBrockman B13 Jo Lab
Start May 1, 2025End Aug 31, 2025
Open record
August 31, 2025
TABS2025013599
2025
Sep 1
7 mos ago
Construction Start
TDLR ProjectProjected start
Work itemAnderson Hall Millwork
Start Sep 1, 2025End May 31, 2026
Open record
September 1, 2025
TABS2025023008
2025
Sep 4
7 mos ago
TDLR Project: Rice GRB E225E Zofchak lab
TDLR ProjectProject Registered
Valuation: $350K
Linked via: Merged
Open record
September 4, 2025
TABS2026000322
2025
Sep 10
7 mos ago
TDLR Project: Rice University Tennis Complex
TDLR ProjectReview Complete
Valuation: $1.4M
Linked via: Merged
Open record
September 10, 2025
TABS2026000643
2025
Sep 19
6 mos ago
TDLR Project: Rice BH 350 - Garg Lab
TDLR ProjectReview Complete
Valuation: $500K
Linked via: Merged
Open record
September 19, 2025
TABS2026001378
2025
Sep 22
6 mos ago
TDLR Project: Rice Duncan 2032 LiKamWa Lab
TDLR ProjectReview Complete
Valuation: $200K
Linked via: Merged
Open record
September 22, 2025
TABS2026001509
2025
Sep 29
6 mos ago
TDLR Project: SEWALL HALL RENOVATION, RICE UNIVERSITY
TDLR ProjectReview Complete
Valuation: $700K
Linked via: Merged
Open record
September 29, 2025
TABS2026002046
2025
Sep 30
6 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice Keck 213 Glasscock Lab
Start Jun 9, 2025End Sep 30, 2025
Open record
September 30, 2025
TABS2025014750
2025
Oct 15
5 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice University TDSP Renovation
Start Oct 15, 2025End Jan 31, 2026
Open record
October 15, 2025
TABS2025025448
2025
Nov 1
5 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice GRB E225E Zofchak lab
Start Nov 1, 2025End Feb 28, 2026
Open record
November 1, 2025
TABS2026000322
2025
Nov 3
5 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice BH 350 - Garg Lab
Start Nov 3, 2025End Feb 27, 2026
Open record
November 3, 2025
TABS2026001378
2025
Dec 1
4 mos ago
Construction Start
TDLR ProjectProjected start
Work itemRice Duncan 2032 LiKamWa Lab
Start Dec 1, 2025End May 31, 2026
Open record
December 1, 2025
TABS2026001509
2025
Dec 5
4 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemPirie & SEA Lab Build-Out
Start May 28, 2025End Dec 5, 2025
Open record
December 5, 2025
TABS2025016697
2025
Dec 18
3 mos ago
TDLR Project: Lab Interior Renovation, Suites 260 and 261
TDLR ProjectReview Complete
Valuation: $2.0M
Linked via: Merged
Open record
December 18, 2025
TABS2026008519
2025
Dec 31
3 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemGRB 3rd Floor Autoclave
Start May 1, 2025End Dec 31, 2025
Open record
December 31, 2025
TABS2025013201
2026
Jan 2
3 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice University McNair Hall Expansion
Start Feb 2, 2024End Jan 2, 2026
Open record
January 2, 2026
TABS2024004284
2026
Jan 5
3 mos ago
Construction Start
TDLR ProjectProjected start
Work itemLab Interior Renovation, Suites 260 and 261
Start Jan 5, 2026End May 1, 2026
Open record
January 5, 2026
TABS2026008519
2026
Jan 13
2 mos ago
TDLR Project: The Original Lovett College Renovation
TDLR ProjectProject Registered
Valuation: $2.9M
Linked via: Merged
Open record
January 13, 2026
TABS2026009932
2026
Jan 26
2 mos ago
Construction Start
TDLR ProjectProjected start
Work itemSEWALL HALL RENOVATION, RICE UNIVERSITY
Start Jan 26, 2026End Jul 31, 2026
Open record
January 26, 2026
TABS2026002046
2026
Jan 31
2 mos ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice University TDSP Renovation
Start Oct 15, 2025End Jan 31, 2026
Open record
January 31, 2026
TABS2025025448
2026
Feb 9
1 mo ago
TDLR Project: Rice Keck Hall Lab 226 Renovation
TDLR ProjectProject Registered
Valuation: $87.5M
Link confidence: 100%
Open record
February 9, 2026
TABS2026012036
2026
Feb 27
25 days ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice BH 350 - Garg Lab
Start Nov 3, 2025End Feb 27, 2026
Open record
February 27, 2026
TABS2026001378
2026
Feb 28
24 days ago
Expected Completion
TDLR ProjectProjected completion
Work itemRice GRB E225E Zofchak lab
Start Nov 1, 2025End Feb 28, 2026
Open record
February 28, 2026
TABS2026000322
2026
Mar 19
5 days ago
TDLR Project: Rice University Security Booth
TDLR ProjectProject Registered
Valuation: $305K
Link confidence: 100%
Open record
March 19, 2026
TABS2026015486
2026
Mar 21
3 days ago
Construction Start
TDLR ProjectProjected start
Work itemRice University Tennis Complex
Start Mar 21, 2026End Mar 21, 2027
Open record
March 21, 2026
TABS2026000643
2026
Apr 6
13 days from now
Construction Start
TDLR ProjectProjected start
Work itemRice Keck Hall Lab 226 Renovation
Start Apr 6, 2026End Aug 28, 2026
Open record
April 6, 2026
TABS2026012036
2026
May 1
1 mo from now
Expected Completion
TDLR ProjectProjected completion
Work itemLab Interior Renovation, Suites 260 and 261
Start Jan 5, 2026End May 1, 2026
Open record
May 1, 2026
TABS2026008519
2026
May 11
2 mos from now
Construction Start
TDLR ProjectProjected start
Work itemThe Original Lovett College Renovation
Start May 11, 2026End Aug 31, 2026
Open record
May 11, 2026
TABS2026009932
2026
May 23
2 mos from now
Construction Start
TDLR ProjectProjected start
Work itemRice University Security Booth
Start May 23, 2026End Sep 1, 2026
Open record
May 23, 2026
TABS2026015486
2026
May 31
2 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemAnderson Hall Millwork
Start Sep 1, 2025End May 31, 2026
Open record
May 31, 2026
TABS2025023008
2026
May 31
2 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemRice Duncan 2032 LiKamWa Lab
Start Dec 1, 2025End May 31, 2026
Open record
May 31, 2026
TABS2026001509
2026
Jun 1
2 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemRICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
Start Jun 1, 2025End Jun 1, 2026
Open record
June 1, 2026
TABS2025013729
2026
Jun 1
2 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemRICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
Start Jun 1, 2025End Jun 1, 2026
Open record
June 1, 2026
TABS2025013727
2026
Jul 31
4 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemSEWALL HALL RENOVATION, RICE UNIVERSITY
Start Jan 26, 2026End Jul 31, 2026
Open record
July 31, 2026
TABS2026002046
2026
Aug 28
5 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemRice Keck Hall Lab 226 Renovation
Start Apr 6, 2026End Aug 28, 2026
Open record
August 28, 2026
TABS2026012036
2026
Aug 31
5 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemThe Original Lovett College Renovation
Start May 11, 2026End Aug 31, 2026
Open record
August 31, 2026
TABS2026009932
2026
Sep 1
5 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemRice University Security Booth
Start May 23, 2026End Sep 1, 2026
Open record
September 1, 2026
TABS2026015486
2027
Mar 21
12 mos from now
Expected Completion
TDLR ProjectProjected completion
Work itemRice University Tennis Complex
Start Mar 21, 2026End Mar 21, 2027
Open record
March 21, 2027
TABS2026000643
2027
Jun 7
1 yr from now
Expected Completion
TDLR ProjectProjected completion
Work itemRice Moody Center For Student Life & Opportunity Phase I
Start May 8, 2025End Jun 7, 2027
Open record
June 7, 2027
TABS2025012057

Linked records by source

TDLR Projects (46)

(source: tabs_projects)
BROCKMAN HALL FOR PHYSICS
Project ClosedFeb 26, 2009
EABPRJA9808796
Description: NEW PHYSICS BUILDINGS
Facility: RICE UNIVERSITY - THE BROCKMAN HALL FOR
Design firm: KIERAN TIMBERLAKE ASSOC.
Estimated cost: $49.0M
DR. PUTNAM LAB RENOVATIONS
Project ClosedMar 10, 2009
EABPRJA9809309
Description: 2304 SF renovation to existing research biology lab space.
Facility: RICE UNIVERSITY
Design firm: CURRY BOUDREAUX ARCHITECTS
Estimated cost: $400K
RICE UNIVERSITY HANSZEN MASTER HOUSE
Project ClosedDec 8, 2010
EABPRJB1804477
Description: Occupancy conversion from residential to business. Not altering a primary function. Modifying entrance walkway t
Facility: HANSZEN MASTER HOUSE
Estimated cost: $100K
SPACE SCIENCE & TECH BLDG RENOVATION
Inspection CompleteApr 24, 2017
EABPRJB7815617
Description: Renovate 3 stories and 1 basement level as new labs withancillary office space.
Facility: SPACE SCIENCE AND TECHNOLOGY BUILDING
Design firm: HOK
Estimated cost: $25.3M
Martel College Suite 1160
Project ClosedMar 7, 2019
TABS2019006459
Description: interior remodel
Facility: Rice University
Estimated cost: $250K
Sq Ft: 2,111
Duncan College Student Activity Space
Project ClosedMar 7, 2019
TABS2019006455
Description: interior remodel
Facility: Duncan Hall
Estimated cost: $150K
Sq Ft: 945
Cohen House Restroom Renovation
Project ClosedApr 8, 2019
TABS2019008805
Description: Renovation of existing restrooms
Facility: Cohen House
Design firm: Courtney Harper and Partners
Estimated cost: $332K
Sq Ft: 800
Rice Volleyball Team Room Renovation
Project ClosedFeb 27, 2020
TABS2020012551
Description: Replacement of interior finishes, lighting, hvac improvement
Facility: Tudor Fieldhouse
Design firm: Jackson & Ryan Architects
Estimated cost: $95K
Sq Ft: 800
MD ANDERSON BIOLOGY 280: EVANS LAB
Project ClosedMar 13, 2020
TABS2020013701
Description: Build out of new laboratory in existing shell space of laboratory building
Facility: RICE UNIVERSITY MD ANDERSON BIOLOGY BLDG
Design firm: Scientia Architects
Estimated cost: $250K
Sq Ft: 900
National Research Security Accelerator
Project ClosedMar 13, 2020
TABS2020013700
Description: Renovation of an existing laboratory with a new laboratory for employee research (no students)
Facility: Dell Butcher Hall
Design firm: Scientia Architects
Estimated cost: $1.2M
Sq Ft: 3,158
APBH Renovations
Project ClosedMay 28, 2020
TABS2020018014
Description: interior renovation of practice rooms in music scholl
Facility: Alice Pratt Brown Hall
Estimated cost: $250K
Sq Ft: 1,800
Rice University PCF 4
Project ClosedJun 30, 2020
TABS2020019842
Description: new tensile membrane structure
Facility: PCF 4
Estimated cost: $500K
Sq Ft: 3,750
Rice University PCF 3
Project ClosedJun 30, 2020
TABS2020019841
Description: new tensile membrane structure
Facility: PCF 3
Estimated cost: $500K
Sq Ft: 3,750
Rice University - AT - Keith-Weiss
Project ClosedJul 30, 2020
TABS2020021447
Description: Tensile Membrane Structure
Facility: At - Keith-Weiss
Estimated cost: $94K
Sq Ft: 2,400
Rice Universtity - AT - West Quad
Project ClosedJul 30, 2020
TABS2020021439
Description: Tensile Structure
Facility: AT - West Quad
Estimated cost: $94K
Sq Ft: 2,400
Rice Sewall Hall
Project ClosedOct 1, 2020
TABS2021001820
Description: An interior renovation of an office suite on the ground floor of a 5 story building. The existing building has two underground levels and the ground floor is on the third floor.
Facility: Rice University, Sewall Hall
Design firm: Gensler
Estimated cost: $381K
Sq Ft: 2,730
OConner Engineering Huang Kono Basement Renovation
Project ClosedSep 26, 2023
TABS2024001735
Description: Small renovation of existing work. Moving a wall, some electrical.
Facility: O'Conner Engineering and Sciences Building
Design firm: Scientia Architects
Estimated cost: $150K
Sq Ft: 1,650
Rice University McNair Hall Expansion
Review CompleteOct 30, 2023
TABS2024004284
Description: 95,000 sf addition to 376,000 sf existing 4 story building, including classrooms, offices, assembly spaces, and existing parking garage. There is no parking scope.
Facility: McNair Hall
Design firm: Kirksey
Estimated cost: $56.7M
Sq Ft: 470,816
Graduate Art Studios
Project ClosedOct 31, 2023
TABS2024004377
Description: Interior Renovation
Facility: PCF 2
Estimated cost: $247K
Sq Ft: 3,750
Rice GRB E225 Kampouri Lab
Project ClosedNov 6, 2023
TABS2024004795
Description: minor interior remodel of existing lab
Facility: George R Brown Hall
Estimated cost: $320K
Sq Ft: 1,283
Anderson Hall Accessible Ramp
Review CompleteSep 25, 2024
TABS2025001841
Description: Adding an accessible entry ramp
Facility: Anderson Hall
Estimated cost: $257K
Sq Ft: 1,200
Gibbs Recreation and Wellness Center
Review CompleteDec 10, 2024
TABS2025007312
Description: Landscape development
Facility: Rice University
Design firm: Bruno Land Design
Estimated cost: $90K
Sq Ft: 2,000
Cannady Hall Shop Office
Project ClosedDec 11, 2024
TABS2025007448
Description: Interior Renovation
Facility: Canady Hall
Estimated cost: $60K
Sq Ft: 215
Rice Boulevard HAWK Crossing
Inspection CompleteJan 14, 2025
TABS2025009493
Description: Installation if new accessible signalized crossing with raised crosswalk
Facility: Rice University Campus
Design firm: TEI
Estimated cost: $250K
Sq Ft: 1
Rice DBH 276 Lab
Review CompleteFeb 13, 2025
TABS2025011844
Description: Renovate existing lab space
Facility: Dell Butcher Hall
Estimated cost: $300K
Sq Ft: 378
Rice Moody Center For Student Life & Opportunity Phase I
Review CompleteFeb 17, 2025
TABS2025012057
Description: Enabling Pkg - Lift Station relocation and tree protection
Facility: Rice University
Design firm: Page Southerland Page, Inc.
Estimated cost: $285K
Sq Ft: 2,500
Women's Golf Locker Room
Project ClosedFeb 24, 2025
TABS2025012590
Description: Interior Renovation
Facility: Rice University
Estimated cost: $101K
Sq Ft: 800
GRB 3rd Floor Autoclave
Review CompleteMar 3, 2025
TABS2025013201
Description: Renovate existing Autoclave room
Facility: George R Brown Hall
Estimated cost: $98K
Sq Ft: 78
Brockman B13 Jo Lab
Project ClosedMar 7, 2025
TABS2025013599
Description: Renovate existing lab space
Facility: Rice University Brockman Hall
Estimated cost: $220K
Sq Ft: 1,021
RICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
Review CompleteMar 10, 2025
TABS2025013729
Description: Add a bulk argon gas tank to the existing nitrogen gas yard adjacent to the building. Renovate lab to create a sample room, and a gas cylinder room. Convert labs to a trace metals lab with new casework, new fume hoods.
Facility: KEITH-WIESS GEOLOGICAL BUILDING
Design firm: Dewberry
Estimated cost: $4.1M
Sq Ft: 1,194
RICE UNIVERSITY KEITH-WIESS GEOLOGICAL BUILDING : ZHANG LABORATORIES
Review CompleteMar 10, 2025
TABS2025013727
Description: Build a small office in lab for a new microscope station. Add a standard laboratory fume hood to lab. Update existing finishes.
Facility: KEITH-WIESS GEOLOGICAL BUILDING
Design firm: Dewberry
Estimated cost: $192K
Sq Ft: 512
Rice Keck 213 Glasscock Lab
Project ClosedMar 20, 2025
TABS2025014750
Description: renovate existing lab space
Facility: Keck Hall
Estimated cost: $650K
Sq Ft: 1,744
Lovett College Renovations
Project ClosedMar 31, 2025
TABS2025015503
Description: guardrail and handrail replacement, egress lighting and fire alarm upgrades, thermal performance improvement, IDF improvements
Facility: Lovett College at Rice University
Design firm: Jackson & Ryan Architects
Estimated cost: $930K
Sq Ft: 21,500
Pirie & SEA Lab Build-Out
Review CompleteApr 15, 2025
TABS2025016697
Description: FINISH OUT OF SHELL SPACES WITHIN A PORTION OF THE BASEMENT FLOOR OF THE O'CONNOR ENGINEERING BUILDING. SCOPE OF WORK INCLUDES NEW RESEARCH LABORATORY SPACE AND SUPPORTING BUILDING SYSTEMS. NO CHANGES TO OCCUPANCY, EGRESS, OR PLUMBING FIXTURE COUNTS.
Facility: O'Connor Engineering Building
Design firm: Scientia Architects
Estimated cost: $1.6M
Sq Ft: 2,224
Rice Ghonasgi Lab Renovation s MEB
Review CompleteMay 6, 2025
TABS2025018272
Description: Renovation to existing lab space for robotics.
Facility: Mechanical Engineering Building
Design firm: PhiloWilke Partnership
Estimated cost: $170K
Sq Ft: 570
Anderson Hall Millwork
Review CompleteJul 8, 2025
TABS2025023008
Description: Installing millwork and adding 3 doors.
Facility: Anderson Hall
Estimated cost: $284K
Sq Ft: 1,270
Rice University TDSP Renovation
Project RegisteredAug 8, 2025
TABS2025025448
Description: renovate existing office space
Facility: Police Building
Estimated cost: $600K
Sq Ft: 5,420
Rice GRB E225E Zofchak lab
Project RegisteredSep 4, 2025
TABS2026000322
Description: Renovate existing lab space
Facility: Rice George R Brown Hall
Estimated cost: $350K
Sq Ft: 1,402
Rice University Tennis Complex
Review CompleteSep 10, 2025
TABS2026000643
Description: Air Supported Tennis Court Cover
Facility: Rice University Tennis Complex
Estimated cost: $1.4M
Sq Ft: 12,960
Rice BH 350 - Garg Lab
Review CompleteSep 19, 2025
TABS2026001378
Description: 911 SF OF RENOVATION WORK WITHIN EXISTING LAB SPACE IN PORTION OF THE THIRD FLOOR OF BROCKMAN HALL. SCOPE OF WORK INCLUDES MEP IMPROVEMENTS AND MINOR ARCHITECTURAL WORK TO SERVE LAB. NO BUILDING AREA INCREASE OR CHANGE IN OCCUPANCY.
Facility: Brockman Hall for Physics
Design firm: Scientia Architects
Estimated cost: $500K
Sq Ft: 911
Rice Duncan 2032 LiKamWa Lab
Review CompleteSep 22, 2025
TABS2026001509
Description: Renovate existing lab space
Facility: Duncan Hall
Estimated cost: $200K
Sq Ft: 847
SEWALL HALL RENOVATION, RICE UNIVERSITY
Review CompleteSep 29, 2025
TABS2026002046
Description: Renovation of existing offices and classrooms & conversion of storage room into two single use bathrooms.
Facility: Sewall Hall at Rice University
Design firm: JACKSON & RYAN ARCHITECTS
Estimated cost: $700K
Sq Ft: 6,900
Lab Interior Renovation, Suites 260 and 261
Review CompleteDec 18, 2025
TABS2026008519
Description: 3,518 SF INTERIOR RENOVATION ON THE SECOND FLOOR OF THE 6-STORY O’CONNOR ENGINEERING BUILDING. SCOPE OF WORK INCLUDES NEW RESEARCH LAB SPACE AND SUPPORTING BUILDING SYSTEMS. NO CHANGES TO OCCUPANCY TYPE, EGRESS ROUTES, PLUMBING FIXTURE COUNTS.
Facility: Ralph S. O’Connor Building for Engineering and Science
Design firm: Scientia Architects
Estimated cost: $2.0M
Sq Ft: 3,518
The Original Lovett College Renovation
Project RegisteredJan 13, 2026
TABS2026009932
Description: Renovation of existing 1st floor dormitory and associated accessory spaces. Convert existing rooms into a laundry room for the dormitory. Upgrade parts of MEP in the building.
Facility: The Original Lovett College
Design firm: Jackson & Ryan Architects
Estimated cost: $2.9M
Sq Ft: 2,705
Rice Keck Hall Lab 226 Renovation
Project RegisteredFeb 9, 2026
TABS2026012036
Description: 1750 sqft interior renovation
Facility: Keck Hall
Design firm: Hellmuth, Obata & Kassabaum, Inc.
Estimated cost: $875K
Sq Ft: 1,750
Rice University Security Booth
Project RegisteredMar 19, 2026
TABS2026015486
Description: New construction of security booth at existing asphalt parking lot to be occupied by one worker at a time. No public access.
Facility: Rice Security Booth
Estimated cost: $305K
Sq Ft: 75

Quick Actions

View on TDLRSatellite View
TDLR ID: EABPRJA9808796

Companies & Contacts

🏢
Owner
William Marsh Rice University
🏢
Owner
RICE UNIVERSITY
🏢
Design firm
KIERAN TIMBERLAKE ASSOC.
🏢
Design firm
CURRY BOUDREAUX ARCHITECTS
🏢
Owner
RICE UNIVERISTY
🏢
Design firm
HOK
🏢
Design firm
Courtney Harper and Partners
🏢
Design firm
Jackson & Ryan Architects
🏢
Design firm
Scientia Architects
🏢
Owner
Rice Universtiy
🏢
Design firm
Gensler
🏢
Design firm
Kirksey
🏢
Design firm
Bruno Land Design
🏢
Design firm
TEI
🏢
Owner
WM Rice Institute
🏢
Design firm
Page Southerland Page, Inc.
🏢
Design firm
Dewberry
🏢
Design firm
Jackson & Ryan Architects
🏢
Design firm
PhiloWilke Partnership
🏢
Owner
WM RICE UNIVERSITY
🏢
Design firm
Hellmuth, Obata & Kassabaum, Inc.

Project metadata

First activity
February 26, 2009
Last activity
March 19, 2026