โœ…Inspection Complete๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Campbell Road / US-75 SBFR Improvements

2001 N Central Expressway, Richardson, TX 75080, Richardson, TX, 75080
Final Inspection85%

๐Ÿ“ŠProject Metrics

TDLR #TABS2019017483
$1.8M
Project Value
99,750
Square Feet
$18/sqft
Cost/SqFt
2 years
Duration
Registered:Aug 1, 2019
Start:Dec 1, 2019
Target:Nov 15, 2021
โœ…

Inspection Complete

Final inspection completed, awaiting project closure

๐Ÿ“‹Scope of Work

CONSTRUCT AUXILLARY LANE ON CAMPBELL ROAD FROM ALAMO TO COLLINS BOULEVARD. EXTEND SOUTHBOUND RIGHT TURN LANE ON SBFR AT CAMPBELL AND ADD SOUTHBOUND LEFT TURN LANE ON SBFR AT CAMPBELL.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
August 1, 2019
Construction Start
December 1, 2019
Expected Completion
November 15, 2021

๐Ÿ“Location & Views

Open in MapsGet Directions|32.97560, -96.71654