๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

Summer Creek High School Additions and Renovations

14000 Weckford Boulevard, Houston, TX 77044, Houston, TX, 77044
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #TABS2020002322
$5.1M
Project Value
16,000
Square Feet
$319/sqft
Cost/SqFt
9 months
Duration
Registered:Oct 3, 2019
Start:Nov 1, 2019
Target:Aug 5, 2020
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New Gym Addition, Weight Room and Locker Room expansion, associated mechanical, electrical, plumbing and technology.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 3, 2019
Construction Start
November 1, 2019
Expected Completion
August 5, 2020