Summer Creek High School Additions and Renovations
14000 Weckford Boulevard, Houston, TX 77044, Houston, TX, 77044
Completed100%
๐Project Metrics
TDLR #TABS2020002322$5.1M
Project Value
16,000
Square Feet
$319/sqft
Cost/SqFt
9 months
Duration
Registered:Oct 3, 2019
Start:Nov 1, 2019
Target:Aug 5, 2020
๐
Project Closed
Project has been completed and closed
๐Scope of Work
New Gym Addition, Weight Room and Locker Room expansion, associated mechanical, electrical, plumbing and technology.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
October 3, 2019
Construction Start
November 1, 2019
Expected Completion
August 5, 2020
Property Owner
๐ค
Humble Independent School District
4 projects ยท $81.2M
View company profile
10203 Birchridge Drive, Humble, Texas 77338