๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
Quality Implement Abilene
4000 Block of Loop 322, Abilene, TX 79602, Abilene, TX, 79602
Completed100%
๐Project Metrics
TDLR #TABS2020021231$4.0M
Project Value
32,940
Square Feet
$121/sqft
Cost/SqFt
10 months
Duration
Registered:Jul 28, 2020
Start:Sep 1, 2020
Target:Jul 1, 2021
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Construct New Quality Implement Building
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 28, 2020
Construction Start
September 1, 2020
Expected Completion
July 1, 2021
๐Related Projects
Property Owner
๐ค
JEFF TICKNER
Contact: Jeff Tickner
View company profile
PO Box 159, Munday, Texas 76371
Design Firm
๐๏ธ
Eikon Consulting Group
4 projects ยท $27.1M
View all projects
1405 West Chapman Dr, Sanger, Texas 76266