City of Post, Sidewalk Improvements

105 E Main St, Suite 1, Post, TX 79356, Post (Garza County)

TDLR Project: 2
Match confidence95%
tdlr_geo

📍Location & Views

Open in MapsGet Directions|33.19077, -101.37814

📊Project Metrics

TDLR #TABS2020021193
$12.3M
Total Value
Started:Jul 27, 2020
Last activity:Mar 17, 2026
Duration:2059 days

Project timeline

2020
Jul 27
6 yrs ago
TDLR Project: City of Post, Sidewalk Improvements
TDLR ProjectProject Closed
Valuation: $335K
Linked via: Merged
Open record
July 27, 2020
TABS2020021193
2021
Jan 1
5 yrs ago
Construction Start
TDLR ProjectProjected start
Work itemCity of Post, Sidewalk Improvements
Start Jan 1, 2021End May 1, 2021
Open record
January 1, 2021
TABS2020021193
2021
May 1
5 yrs ago
Expected Completion
TDLR ProjectProjected completion
Work itemCity of Post, Sidewalk Improvements
Start Jan 1, 2021End May 1, 2021
Open record
May 1, 2021
TABS2020021193
2026
Mar 17
7 days ago
TDLR Project: City of Post WWTP
TDLR ProjectProject Registered
Valuation: $12.0M
Link confidence: 100%
Open record
March 17, 2026
TABS2026015168
2026
Jun 29
3 mos from now
Construction Start
TDLR ProjectProjected start
Work itemCity of Post WWTP
Start Jun 29, 2026End Oct 29, 2027
Open record
June 29, 2026
TABS2026015168
2027
Oct 29
2 yrs from now
Expected Completion
TDLR ProjectProjected completion
Work itemCity of Post WWTP
Start Jun 29, 2026End Oct 29, 2027
Open record
October 29, 2027
TABS2026015168

Linked records by source

TDLR Projects (2)

(source: tabs_projects)
City of Post, Sidewalk Improvements
Project ClosedJul 27, 2020
TABS2020021193
Description: Replace approximately 573 square yards of 4" sidewalk with a combination of steps, rails, ADA ramps, curb, gutter and associated appurtenances.
Facility: City of Post
Design firm: Jacob Martin, LLC - Allen Phillips
Estimated cost: $335K
Sq Ft: 5,157
City of Post WWTP
Project RegisteredMar 17, 2026
TABS2026015168
Description: Construction of a new mechanical wastewater treatment plant which includes Lift Station, Screening, Aeration Basins, Clarifiers, Phosphorus Removal System, Disinfection Equipment, Sludge Dewatering Equipment, Discharge Structures, and Admin. Building
Facility: Post WWTP
Design firm: Parkhill (Jorge Campos)as
Estimated cost: $12.0M
Sq Ft: 3,531

Quick Actions

View on TDLRSatellite View
TDLR ID: TABS2020021193

Registered Accessibility Specialist

STEPHEN D,MACPHIE (RAS #307)
4210 E MUNICIPAL DR APT 6, LUBBOCK, TX 79403

Companies & Contacts

🏢
Owner
City of Post
🏢
Design firm
Jacob Martin, LLC - Allen Phillips
🏢
Design firm
Parkhill (Jorge Campos)as

Project metadata

First activity
July 27, 2020
Last activity
March 17, 2026