📋 Solicitation✅ Posted
WNF | Front Ave | E. Main St | Settlers
673 days leftDue: June 3, 2028
📄Description
Construct a 2-lane asphalt roadway. This will include the installation of curb and gutter along the project extents. This project will also construct a 10-foot wide shared use path, and reconstruct the current culvert.
Type of Work: Widen Road - Add Lanes And Shoulders
Highway: FRONT AVE
Location: E. Main St to Settlers Point Plaza
County: Bell
Working Days: 180.0
Oversight: State
Spec Book Year: 2024.0
🚧TxDOT Project Details
💲Estimated Cost
$1.49M
Engineer's estimate / low bid estimate from TxDOT
🔗More from TxDOT - Waco District
Key Details
- Solicitation ID
- txdot_0909-36-211
- Source
- TxDOT
- Status
- ✅ Posted
- Open for submissions
- Category
- heavy civil
- Due Date
- June 3, 2028
👤 Contact
Michael Yates
[email protected]🏛️ Agency
TxDOT - Waco District
🏛️ State Agency
Hill, TX
Agency #txdot_waco
View agency profile →View all TxDOT - Waco District bids →View the official TxDOT project data
View on data.texas.gov