Construction complete ยท Nov 2008๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project is privately funded, on private land for private use.

CYRUSONE PHASE 2

2501 SOUTH STATE HIIGHWAY 121, Lewisville, TX 75067, Lewisville, TX, 75067

CYRUSONE PHASE 2 is a additions to existing building project at 2501 SOUTH STATE HIIGHWAY 121, Lewisville, in Denton County, TX, tracked from its Texas Department of Licensing and Regulation (TDLR) registration. Construction complete (TDLR inspection passed Nov 2008). The project has an estimated value of $70K.

Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9800436
$70K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
2 months
Duration
Registered:Sep 8, 2008
Start:Sep 1, 2008
Target:Nov 1, 2008
๐Ÿ

Project Closed

Project has been completed and closed

CYRUSONE PHASE 2 is a Additions to Existing Building project located at 2501 SOUTH STATE HIIGHWAY 121, Lewisville, TX 75067 in Lewisville, Texas. The project has an estimated value of $70K. BREOF CONVERGENCE LP is the property owner and DUANE BRADSHAW ARCHITECTS is the design firm of record. The project was registered with TDLR on September 8, 2008.

โ“Frequently Asked Questions

What is CYRUSONE PHASE 2?

CYRUSONE PHASE 2 is a additions to existing building project at 2501 SOUTH STATE HIIGHWAY 121 in Lewisville, Texas, registered with the Texas Department of Licensing and Regulation (TDLR). Scope of work: Phase 2 Buildout of a Data Center in an Existing Building

Is CYRUSONE PHASE 2 open in Lewisville?

Construction on CYRUSONE PHASE 2 is complete โ€” TDLR records show the project passed its required accessibility inspection in Nov 2008. The building is finished and very likely open.

Where is CYRUSONE PHASE 2 located?

CYRUSONE PHASE 2 is located at 2501 SOUTH STATE HIIGHWAY 121, Lewisville, TX, 75067, in Denton County.

Who is the owner or developer of CYRUSONE PHASE 2?

BREOF CONVERGENCE LP is the property owner/developer of record for CYRUSONE PHASE 2, per its TDLR project registration.

Who is the architect or design firm for CYRUSONE PHASE 2?

DUANE BRADSHAW ARCHITECTS is the design firm of record for CYRUSONE PHASE 2, according to its TDLR filing.

How much does CYRUSONE PHASE 2 cost and how big is it?

CYRUSONE PHASE 2 has an estimated construction value of $70K, based on its TDLR filing.

๐Ÿ“‹Scope of Work

Phase 2 Buildout of a Data Center in an Existing Building

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 8, 2008
Project Closed
November 1, 2008
Construction Start
September 1, 2008
Expected Completion
November 1, 2008

๐Ÿ“…Project Timeline

Filed

Sep 8, 2008

Review Complete

Inspection Complete

Closed

Nov 1, 2008

๐Ÿ“Location & Views

Open in MapsGet Directions|33.00056, -96.99653

๐Ÿ”—Related Projects

Get alerts for Denton

Daily email when new projects start nearby.

Start Alerts - $19/mo

Download project data

Get curated lists of projects with full contact info.

Browse Data Lists