EARLY COLLEGE HIGH SCHOOL

2510 PECAN, Harlingen, TX 78550, Harlingen, TX, 78550
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9801906
$1.4M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1 year
Duration
Registered:Oct 3, 2008
Start:Dec 1, 2008
Target:Dec 1, 2009
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Additions to existing High School.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 3, 2008
Construction Start
December 1, 2008
Expected Completion
December 1, 2009