๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

REPLACEMENT&ARTIFICIAL TURF INSTALLATION

8540 C.E. KING PARKWAY, Houston, TX 77044, Houston, TX, 77044
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJA9808827
$1.5M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Feb 27, 2009
Start:Mar 1, 2009
Target:Jul 1, 2009
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Track replacement and artificial turf installation.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 27, 2009
Construction Start
March 1, 2009
Expected Completion
July 1, 2009

๐Ÿ“Location & Views

Open in MapsGet Directions|29.84890, -95.21407