๐Project Metrics
TDLR #EABPRJA9814011$3.9M
Project Value
โ
Square Feet
โ
Cost/SqFt
11 months
Duration
Registered:Jun 19, 2009
Start:Sep 1, 2009
Target:Aug 1, 2010
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Build a concrete road (3800 linear ft). Drainage, pavingand utility improvements.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
June 19, 2009
Project Closed
August 1, 2010
Construction Start
September 1, 2009
Expected Completion
August 1, 2010
๐Related Projects
๐คSame Owner
$4.4M total๐Nearby Projects
Within 1 kmCollins Blvd Overpass (CSJ: 0918-47-401)
From: Campbell Rd To: Alma Rd, Richardson, TX 75080ยท$875K
CFA 06177 Sachse
SEC Miles Rd & The Station Blvd, Sachse, TX 75048ยท$4.5M
Pedestrian Improvements - S. Lancaster Road from E. Kiest Blvd. to E. Ledbetter Road
Varies - Seven Intersections along S. Lancaster Rd, Dallas, TX 75216ยท$195K
MCD 67 & WINTERGREEN - CEDAR HILL, TX
SEC US 67 & WINTERGREEN RD, Cedar Hill, TX 75104ยท$1.5M
Property Owner
๐ค
PACTRUST
Contact: Registered by TDLR
3 projects ยท $4.4M
View company profile
MATT OYEN 15350 SEQUOIA PARKWAY, PORTLAND, OR 97224
Design Firm
๐๏ธ
HALFF ASSOCIATES
4 projects ยท $5.0M
View all projects
JORGE L. RODRIGUEZ 1201 NORTH BOWSER RD, RICHARDSON, TX 75081