πProject Closedπ§ Alteration/Renovation
HARDEMAN COUNTY COURTHOUSE: EXTERIOR RES
Completed100%
πProject Metrics
TDLR #EABPRJB0000966$2.2M
Project Value
β
Square Feet
β
Cost/SqFt
1y 3mo
Duration
Registered:Jun 29, 2010
Start:Jul 1, 2010
Target:Oct 1, 2011
π
Project Closed
Project has been completed and closed
π Compliance Timeline
Project Registered
June 29, 2010
Construction Start
July 1, 2010
Expected Completion
October 1, 2011