๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

RTA ADA BUS STOP IMPROVEMENTS- ZONE 3

VARIOUS, Corpus Christi, TX 78408, Corpus Christi, TX, 78408
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB0802105
$637K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Oct 19, 2009
Start:Dec 1, 2009
Target:May 1, 2010
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

ADA curb ramps and Bus Stops at various locations in theCity of Corpus Christi

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 19, 2009
Construction Start
December 1, 2009
Expected Completion
May 1, 2010