๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

GSA TIMPO DATA CENTER

300 CONVENT, San Antonio, TX 78205, San Antonio, TX, 78205
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB0806106
$5.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Jan 26, 2010
Start:Feb 1, 2010
Target:Jun 1, 2010
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

renovation of 3rd floor existing office space into a computer server room and 1st floor garage level existing dr

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 26, 2010
Construction Start
February 1, 2010
Expected Completion
June 1, 2010