GSA TIMPO DATA CENTER
300 CONVENT, San Antonio, TX 78205, San Antonio, TX, 78205
Completed100%
๐Project Metrics
TDLR #EABPRJB0806106$5.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
4 months
Duration
Registered:Jan 26, 2010
Start:Feb 1, 2010
Target:Jun 1, 2010
๐
Project Closed
Project has been completed and closed
๐Scope of Work
renovation of 3rd floor existing office space into a computer server room and 1st floor garage level existing dr
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 26, 2010
Construction Start
February 1, 2010
Expected Completion
June 1, 2010
๐Related Projects
๐คSame Owner
$1.1M total๐๏ธSame Design Firm
$864K totalProperty Owner
๐ค
TALCOTT II ALAMO LIMITED
4 projects ยท $1.1M
View company profile
MARTIN KANE 300 CONVENT, SUITE 2424, SAN ANTONIO, TX 78205
Design Firm
๐๏ธ
CARSON DESIGN ASSOCIATES
4 projects ยท $864K
View all projects
THOMAS KEMP 719 CARNOUSTIE, SUITE 150, SAN ANTONIO, TX 78258