🏁Project Closed🏗️ New Construction💵 This project is privately funded, on private land for private use.
MOUNT CALVARY BAPTIST CHURCH
248 18TH STREET, Port Arthur, TX 77640, Port Arthur, TX, 77640
Completed100%
📊Project Metrics
TDLR #EABPRJB1810273$120K
Project Value
—
Square Feet
—
Cost/SqFt
2y 10mo
Duration
Registered:Apr 11, 2011
Start:Apr 1, 2011
Target:Dec 31, 2013
🏁
Project Closed
Project has been completed and closed
📋Scope of Work
New sanctuary, restrooms, parking
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
📅Compliance Timeline
Project Registered
April 11, 2011
Construction Start
April 1, 2011
Expected Completion
December 31, 2013