๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

DCP MIDSTREAM CONTROL BUILDING

2628 US HIGHWAY 79 NORTH, Carthage, TX 75633, Carthage, TX, 75633
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2800436
$1.8M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
6 months
Duration
Registered:Sep 12, 2011
Start:Sep 1, 2011
Target:Mar 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Pre-fabricated metal Building.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 12, 2011
Construction Start
September 1, 2011
Expected Completion
March 1, 2012