RENOVATIONS @ JR. HIGH GYM AND CAFETERIA

717 E. 6TH STREET, Bishop, TX 78343, Bishop, TX, 78343
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2802478
$500K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Oct 24, 2011
Start:Nov 1, 2011
Target:Mar 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovations and HVAC at WeightRoom and Restrooms at Jr,High Gymnasium and cafeteria

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 24, 2011
Construction Start
November 1, 2011
Expected Completion
March 1, 2012