๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

CAMPBELL CENTER I FL 16 RR & CORR

8350 N. CENTRAL EXPRESSWAY, Dallas, TX 75206, Dallas, TX, 75206
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2809369
$100K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3 months
Duration
Registered:Mar 12, 2012
Start:Mar 1, 2012
Target:Jun 1, 2012
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Renovate Corridor and Restrooms on the 16th floor.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 12, 2012
Construction Start
March 1, 2012
Expected Completion
June 1, 2012