๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

PLANTATION DRIVE NORTH PH I & II

SO. OF FM 3083, Conroe, TX 77301, Conroe, TX, 77301
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2813805
$1.2M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
11 months
Duration
Registered:May 30, 2012
Start:Aug 1, 2012
Target:Jul 1, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

3,780 lf, 64ft wide road with adjacent sidewalk improvements

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
May 30, 2012
Construction Start
August 1, 2012
Expected Completion