๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
WESTLAKE 4TH FLOOR BUILD OUT
8 CAMPUS CIRCLE, 4TH FLOOR, Westlake, TX 76262, Westlake, TX, 76262
Completed100%
๐Project Metrics
TDLR #EABPRJB2815967$3.3M
Project Value
โ
Square Feet
โ
Cost/SqFt
2 months
Duration
Registered:Jul 6, 2012
Start:Jul 1, 2012
Target:Sep 1, 2012
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Remodel entire 4th floor- zareas admin/Lab (data center)
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 6, 2012
Construction Start
July 1, 2012
Expected Completion
September 1, 2012
๐Related Projects
Property Owner
๐ค
CASSIDY TURLEY MIDWEST INC
View all projects
JOHN COMBS 9 VILLAGE CIRCLE, SUITE 500, WESTLAKE, TX 76262
Design Firm
๐๏ธ
EXP
4 projects ยท $2.0M
View all projects
PARVIZ MAHDAVI 12801 N CENTRAL EXPY, #1170, DALLAS, TX 75234