๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

ALVIN CENTER PHASE II, OUTPARCEL A

162 SOUTH HIGHWAY 35 BY-PASS, Alvin, TX 77511, Alvin, TX, 77511
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB2816207
$600K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Jul 11, 2012
Start:Aug 1, 2012
Target:Jan 1, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Site Development Work and Lease Building Shell

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
July 11, 2012
Construction Start
August 1, 2012
Expected Completion
January 1, 2013