๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

BARRYKNOLL LN IMPROV. WBS:T-170015-001-3

BARRYKNOLL LANE, Houston, TX 77024, Houston, TX, 77024
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB3800511
$137K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 4mo
Duration
Registered:Sep 12, 2012
Start:Jan 1, 2013
Target:May 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

STORM DRAIN CONSTRUCTION, WATER AND SANITARY SEWER CONSTROADWAY RECONSTRUCTION, SIDEWALK CONSTRUCTION RV250

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
September 12, 2012
Construction Start
January 1, 2013
Expected Completion
May 1, 2014