๐Project Closed๐ง Renovation/Alteration๐ต This project is privately funded, on private land for private use.
MH ADVANCED HEART FAILURE CLINIC
6400 FANNIN ST Suite 2500, Houston, TX 77030, Houston, TX, 77030
Completed100%
๐Project Metrics
TDLR #EABPRJB3808344$1.6M
Project Value
โ
Square Feet
โ
Cost/SqFt
5 months
Duration
Registered:Feb 12, 2013
Start:May 1, 2013
Target:Oct 1, 2013
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Interior renovation on the 25th floor of an existing Medical Office Building for new clinic.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 12, 2013
Project Closed
October 1, 2013
Construction Start
May 1, 2013
Expected Completion
October 1, 2013
๐Related Projects
๐คSame Owner
$2.8M total๐Nearby Projects
Within 1 kmBen Taub Hospital Campus - Switchgear, ATS and Generator Installation
1504 Taub Loop, Houston, TX 77030ยท$13.3M
HM SCUR - PO Neuro Pain - Public Corridor
6560 Fannin Street 950, Houston, TX 77030ยท$200K
HM SCUR - PO Neuro Pain - Suite 900
6560 Fannin Street 900, Houston, TX 77030ยท$2.5M
HM SCUR - PO Neuro Pain - Suite 950
6560 Fannin Street 950, Houston, TX 77030ยท$523K
Property Owner
๐ค
Memorial Hermann Medical Plaza JLL
Contact: Registered by TDLR
3 projects ยท $2.8M
View company profile
ROBIN HARRISON 6400 FANNIN ST, HOUSTON, TX 77030
Design Firm
๐๏ธ
Curry Boudreaux Architects
4 projects ยท $5.2M
View company profile
STEVEN F. CURRY 5009 CAROLINE, SUITE 200, HOUSTON, TX 77004