๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project is privately funded, on private land for private use.

HARDY OAK MEDICAL OFFICE BLDG.-PHASE 1

MEISNER DRIVE & HARDY OAK BLVD, San Antonio, TX 78258, San Antonio, TX, 78258
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4802061
$2.9M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 10mo
Duration
Registered:Oct 7, 2013
Start:Nov 1, 2013
Target:Aug 31, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Phase 1 of a new, multi-tenant, two-story medical officebuilding, approx. 26,000 sf.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
October 7, 2013
Construction Start
November 1, 2013
Expected Completion
August 31, 2015