๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

HOUSTON CHRONICLE REVISED HIGH PILE STOR

4747 SOUTHWEST FREEWAY, Houston, TX 77027, Houston, TX, 77027
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4805483
$220K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Dec 5, 2013
Start:Jan 1, 2014
Target:May 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Revisions to the high pile storage

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 5, 2013
Project Closed
May 1, 2014
Construction Start
January 1, 2014
Expected Completion
May 1, 2014