๐ŸProject Closed๐Ÿ”ง Additions to Existing Building๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

JEFFERSON ELEM. SCHOOL ADDITION & RENO.

601 S. J STREET, Harlingen, TX 78550, Harlingen, TX, 78550
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4806852
$2.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
10 months
Duration
Registered:Jan 2, 2014
Start:Jan 1, 2014
Target:Nov 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Demolition of an existing 10,529 sf. wing & replaced itwith a 6,844 sf. wing or 9,091 sf. if bid alternate is a

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 2, 2014
Construction Start
January 1, 2014
Expected Completion
November 1, 2014