๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project is privately funded, on private land for private use.

CENTERPOINT ENERGY ADDICKS OPS PHASE 2

3333 BRITTMOORE RD, Houston, TX 77043, Houston, TX, 77043
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4806861
$33.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
9 months
Duration
Registered:Jan 2, 2014
Start:Mar 1, 2014
Target:Dec 1, 2014
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

New tenant build out (data center) in existing 2 story shell space & addition of one story transformer vault & c

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
January 2, 2014
Project Closed
December 1, 2014
Construction Start
March 1, 2014
Expected Completion
December 1, 2014