🏁Project Closed🔧 Renovation/Alteration💵 This project is privately funded, on private land for private use.

MR. CARTENDER

NE CORNER HWY 57 AND HWY 277, Eagle Pass, TX 78852, Eagle Pass, TX, 78852
Completed100%

📊Project Metrics

TDLR #EABPRJB4808267
$900K
Project Value
Square Feet
Cost/SqFt
1 year
Duration
Registered:Jan 28, 2014
Start:Mar 1, 2014
Target:Mar 1, 2015
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

Fire damage replacement building on existing foundation

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
January 28, 2014
Construction Start
March 1, 2014
Expected Completion
March 1, 2015