๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

AVALON AT RIVERSTONE - SECTION 7

TILLBUSTER PONDS CT., Sugar Land, TX 77479, Sugar Land, TX, 77479
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4812003
$500K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
11 months
Duration
Registered:Mar 28, 2014
Start:May 1, 2014
Target:Mar 15, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Sidewalks, Gated Entry, Planting and Irrigation

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
March 28, 2014
Construction Start
May 1, 2014
Expected Completion
March 15, 2015