Inspection Complete๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
REPLACEMENT ATC-STINSON MUNICIPAL AIRPOR
1283 E ASHLEY ROAD, San Antonio, TX 78214, San Antonio, TX, 78214
Final Inspection85%
๐Project Metrics
TDLR #EABPRJB4815711$2.6M
Project Value
โ
Square Feet
โ
Cost/SqFt
3y 10mo
Duration
Registered:May 23, 2014
Start:Oct 1, 2014
Target:Jun 29, 2018
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
Construct new Airport Traffic Control Tower comprised of10 levels, 99'9" cab floor level above ground. Tower fo
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
May 23, 2014
Inspection Complete
June 29, 2018
Construction Start
October 1, 2014
Expected Completion
June 29, 2018
Property Owner
๐ค
CITY OF SAN ANTONIO
4 projects ยท $1.4M
View company profile
LOYCE D. CLARK 9800 AIRPORT BLVD, SAN ANTONIO, TX 78216
Design Firm
๐๏ธ
AJT ENGINEERING INC
View company profile
PETER DEEKS 200 WILLARD STREET, STE 2C, COCOA, FL 32922