๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

BINZ-ENGLEMAN RD SIDEWALK IMPROVEMENT

BEXAR COUNTY, San Antonio, TX 78109, San Antonio, TX, 78109
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4817679
$95K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
7 months
Duration
Registered:Jun 25, 2014
Start:Jun 1, 2014
Target:Jan 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Sidewalk and Drainage Improvements

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
June 25, 2014
Construction Start
June 1, 2014
Expected Completion
January 1, 2015