๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

NEWDOORSATLECTUREH.FOYERWO#336042

7703 FLOYD CURL, San Antonio, TX 78229, San Antonio, TX, 78229
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5806586
$100K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1 months
Duration
Registered:Dec 15, 2014
Start:Mar 1, 2015
Target:Apr 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Add new doors to Lecture Hall foyer 3.1

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 15, 2014
Project Closed
April 1, 2015
Construction Start
March 1, 2015
Expected Completion