🏁Project Closed🏗️ New Construction💵 This project is privately funded, on private land for private use.

BUILDING O WAREHOUSE FACILITY

12130 SARA RD., Laredo, TX 78045, Laredo, TX, 78045
Completed100%

📊Project Metrics

TDLR #EABPRJB5809557
$5.0M
Project Value
Square Feet
Cost/SqFt
6 months
Duration
Registered:Feb 6, 2015
Start:Mar 1, 2015
Target:Sep 1, 2015
🏁

Project Closed

Project has been completed and closed

📋Scope of Work

The scope of the work includes but is not limited to site grading, retaining walls, concrete and asphalt parking

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

📅Compliance Timeline

Project Registered
February 6, 2015
Construction Start
March 1, 2015
Expected Completion
September 1, 2015