๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

ECISD HERITAGE MS GYM FLOOR REPLACEMENT

8004 NEW SULPHUR SPRINGS ROAD, San Antonio, TX 78263, San Antonio, TX, 78263
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5809662
$220K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
4 months
Duration
Registered:Feb 9, 2015
Start:Mar 1, 2015
Target:Jul 1, 2015
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Demolition of old PVC floor and installation of new woodfloor at 2 Gymnasiums.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
February 9, 2015
Construction Start
March 1, 2015
Expected Completion
July 1, 2015