๐ŸProject Closed๐Ÿ”ง Renovation/Alteration๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

CROSBY LYNCHBURG PHASE 2

ARCADIAN DRIVE TO MAGNOLIA ST., Crosby, TX 77532, Crosby, TX, 77532
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB5813967
$4.0M
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
1y 5mo
Duration
Registered:Apr 16, 2015
Start:Aug 1, 2015
Target:Jan 5, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Concrete undivided road with a continuous left turn lane, to include storm sewer and sidewalk.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
April 16, 2015
Construction Start
August 1, 2015
Expected Completion
January 5, 2017