โ
Inspection Complete๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
PHASE ONE RELOCATION
112 N COLORADO ST, Celina, TX 75009, Celina, TX, 75009
Final Inspection85%
๐Project Metrics
TDLR #EABPRJB5820067$6.5M
Project Value
โ
Square Feet
โ
Cost/SqFt
10 months
Duration
Registered:Jul 16, 2015
Start:Aug 1, 2015
Target:Jun 1, 2016
โ
Inspection Complete
Final inspection completed, awaiting project closure
๐Scope of Work
New 13,000 sf One story Building, walks, drives and parking.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
July 16, 2015
Construction Start
August 1, 2015
Expected Completion
June 1, 2016
๐Related Projects
๐๏ธSame Design Firm
$11.8M totalProperty Owner
๐ค
FIRST UNITED METHODIST CHURCH CELINA
View company profile
JOHN HERRIN 112 N COLORADO ST, CELINA, TX 75009
Design Firm
๐๏ธ
BBA A
3 projects ยท $11.8M
View company profile
J. HARDY BROWN 902 WAYSIDE WAY, RICHARDSON, TX 75080