๐Project Closed๐๏ธ New Construction๐ต This project involves public funds, public land, or is a Federally funded roadway project.
HOLLISTER ROAD PAVING & DRAINAGE
WHITE OAK BAYOU TO W. GULFBANK (Key Map No. 410 R,V), Houston, TX 77040, Houston, TX, 77040
Completed100%
๐Project Metrics
TDLR #EABPRJB5821432$92K
Project Value
โ
Square Feet
โ
Cost/SqFt
1y 4mo
Duration
Registered:Aug 6, 2015
Start:Feb 1, 2016
Target:May 31, 2017
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Widen existing two-lane roadway section to a four lane boulevard. Work includes grading, paving, curb & gutter,
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
August 6, 2015
Construction Start
February 1, 2016
Expected Completion
May 31, 2017
๐Related Projects
๐๏ธSame Design Firm
$372K totalProperty Owner
๐ค
CITY OF HOUSTON (PWE)
View all projects
STEPHEN CAMPAGNA 611 WALKER ST, HOUSTON, TX 77002
Design Firm
๐๏ธ
PARSONS BRINKERHOFF
2 projects ยท $372K
View company profile