๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

ASHLEY RD PEDESTRIAN BRIDGE

ASHLEY RD From Roosevelt to Acequia, San Antonio, TX 78214, San Antonio, TX, 78214
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6805170
$400K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
5 months
Duration
Registered:Nov 19, 2015
Start:Apr 1, 2016
Target:Sep 1, 2016
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Install Pedestrian Bridge and construct 2 cu del sacs.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 19, 2015
Construction Start
April 1, 2016
Expected Completion
September 1, 2016