๐Project Closed๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
CITY OF LINDALE SIDEWALK IMPROVEMENTS
NW CORNER OF US 69 & FM 16, Lindale, TX 75771, Lindale, TX, 75771
Completed100%
๐Project Metrics
TDLR #EABPRJB6806527$180K
Project Value
โ
Square Feet
โ
Cost/SqFt
7 months
Duration
Registered:Dec 15, 2015
Start:Mar 1, 2016
Target:Oct 1, 2016
๐
Project Closed
Project has been completed and closed
๐Scope of Work
Approx 478 lf concrete sidewalk with curb, gutter, and curb ramps
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 15, 2015
Construction Start
March 1, 2016
Expected Completion
October 1, 2016
๐Related Projects
๐คSame Owner
$2.3M totalProperty Owner
๐ค
CITY OF LINDALE
3 projects ยท $2.3M
View all projects
CAROLYN CALDWELL PO BOX 130, LINDALE, TX 75771
Design Firm
๐๏ธ
ADAMS ENGINEERING
View company profile
STEPHEN G BENNETT 1101 ESE LOOP 323, STE 101, TYLER, TX 75701