IH 10 FRONTAGE ROADS - INTERSECTIONS

FROM BARKER CYPRESS TO KIRKWOO, Houston, TX 77447, Houston, TX, 77447
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB6806880
$270K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
9 months
Duration
Registered:Dec 18, 2015
Start:May 1, 2016
Target:Feb 1, 2017
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Construction of sidewalks & ADA ramps, consisting of grading, base, pavement, and landscape.

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
December 18, 2015
Construction Start
May 1, 2016
Expected Completion