๐Project Closed๐๏ธ New Construction๐ต This project is privately funded, on private land for private use.
KATY STATION PARKING STRUCTURE
NEC HWY 99 AND IH-10, Houston, TX 77449, Houston, TX, 77449
Completed100%
๐Project Metrics
TDLR #EABPRJB6808039$20.0M
Project Value
โ
Square Feet
โ
Cost/SqFt
10 months
Duration
Registered:Jan 13, 2016
Start:Feb 1, 2016
Target:Dec 1, 2016
๐
Project Closed
Project has been completed and closed
๐Scope of Work
6 level, 585,432 sf, precast conc. parking garage for 1,727 parking capacity.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
January 13, 2016
Construction Start
February 1, 2016
Expected Completion
December 1, 2016
๐Related Projects
๐๏ธSame Design Firm
$20.6M totalProperty Owner
๐ค
A 9 98 NEC GRAND PARKWAY IH 10 W
View company profile
STAN BEARD 8827 W. SAM HOUSTON PKWY #200, HOUSTON, TX 77040
Design Firm
๐๏ธ
PAUL F KAHLICH AIA
3 projects ยท $20.6M
View company profile
PAUL F.KAHLICH 7918 SHARPVIEW DR., HOUSTON, TX 77036